Data center buildUnder construction2 of 2 datasets agree

Homer City Energy Campus

Homer City RedevelopmentHomer City, Indiana County, PAUpdated

Homer City Redevelopment is building a 4500 MW data center in Indiana County, Pennsylvania (under construction). 3 sources report this facility in the Kapwork Grow tracker.

Capacity
4500 MW
Investment
$10B
Site
3,200 acres
Expected completion
2027
IT load
3700 MW

Who's on this build

Named in the cited sources. No source reports who builds it.

Schedule

Dates as reported. Not a bid calendar. A planned date is not evidence that work occurred.

  1. next year

    Expected completionPlanned

  2. Today

    Under construction

    Last material change Sep 24, 2026.

  3. 17 mo ago

    Announced

  4. 17 mo ago

    Reported as announced

    Event date: · First observed: Not reported

  5. last year

    Construction start

Reported updates without an event date

Record quality

Datasets
2, all agree
Location
Site footprint confirmed
Summary
From published records
Source as of
Last material change

Site and infrastructure

CA Compute AtlasSC Server CountryPE Public Evidence ProjectKW Kapwork Grow tracker record

Status

Operator
Homer City RedevelopmentOperator · Compute AtlasCompute Atlas facility record (Kubiak, E., 2026, CC BY 4.0)As of Sep 12, 2026 · Record: homer-city-energy-campus-paOperator · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0427
Stage
Under constructionStage · Compute AtlasCompute Atlas facility record (Kubiak, E., 2026, CC BY 4.0)As of Sep 12, 2026 · Record: homer-city-energy-campus-paStage · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0427
Facility type
AI data centerFacility type · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 124238487835890

Scale

Reported capacity
4500 MWReported capacity · Compute AtlasCompute Atlas facility record (Kubiak, E., 2026, CC BY 4.0)As of Sep 12, 2026 · Record: homer-city-energy-campus-paReported capacity · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0427
Reported IT load
3700 MWReported IT load · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 124238487835890
Reported investment
$10BReported investment · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 124238487835890
Site area
3,200 acresSite area · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 124238487835890
Reported jobs
1,000Reported jobs · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 124238487835890

Reported dates

Announced
2025-04-02Announced · Compute AtlasCompute Atlas facility record (Kubiak, E., 2026, CC BY 4.0)As of Sep 12, 2026 · Record: homer-city-energy-campus-paReported date — see the source for the event evidenced.
Construction start reported
2025Construction start reported · Compute AtlasCompute Atlas facility record (Kubiak, E., 2026, CC BY 4.0)As of Sep 12, 2026 · Record: homer-city-energy-campus-pa
Expected completion
2027Expected completion · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0427

Site

City
Homer CityCity · Compute AtlasCompute Atlas facility record (Kubiak, E., 2026, CC BY 4.0)As of Sep 12, 2026 · Record: homer-city-energy-campus-paCity · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0427City · Public Evidence ProjectPublic Evidence Project: Permit from Pennsylvania DEPAs of Aug 6, 2026 · Record: source-homer-city-energy-campus-pa
County
IndianaCounty · Compute AtlasCompute Atlas facility record (Kubiak, E., 2026, CC BY 4.0)As of Sep 12, 2026 · Record: homer-city-energy-campus-paCounty · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0427County · Public Evidence ProjectPublic Evidence Project: Permit from Pennsylvania DEPAs of Aug 6, 2026 · Record: source-homer-city-energy-campus-pa
State
PennsylvaniaState · Compute AtlasCompute Atlas facility record (Kubiak, E., 2026, CC BY 4.0)As of Sep 12, 2026 · Record: homer-city-energy-campus-paState · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0427State · Public Evidence ProjectPublic Evidence Project: Permit from Pennsylvania DEPAs of Aug 6, 2026 · Record: source-homer-city-energy-campus-pa
Location precision
Site footprint confirmedLocation precision · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 124238487835890

Power and cooling

Utility
PJM (via FirstEnergy Pennsylvania Electric)Utility · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 124238487835890
Power source
On-site natural gas generationPower source · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 124238487835890
AI workload
Confirmed AI or machine-learning workloadAI workload · Compute AtlasCompute Atlas facility record (Kubiak, E., 2026, CC BY 4.0)As of Sep 12, 2026 · Record: homer-city-energy-campus-pa

Permits and public records

Government records on file
1Government records on file · Public Evidence ProjectPublic Evidence Project: Permit from Pennsylvania DEPAs of Aug 6, 2026 · Record: source-homer-city-energy-campus-pa
Incentives reported
Pennsylvania state grant — natural-gas pipeline interconnection (Pennsylvania) $5,000,000Incentives reported · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 124238487835890

Sources, method and limits

Show 12 sourcesHide

What each source reports

What each source reports
DatasetReported nameReported statusReported MW
Compute AtlasHomer City Energy CampusUnder construction4500 MW
Server CountryHomer City Energy CampusUnder construction4500 MW

Sources and evidence

  1. CA
    Compute Atlas facility record (Kubiak, E., 2026, CC BY 4.0)As of: Sep 12, 2026 · Record: homer-city-energy-campus-pa
  2. CA
  3. CA
  4. CA
  5. CA
  6. CA
  7. CA
  8. CA
  9. CA
  10. CA
  11. SC
    Server Country project record (CC BY 4.0)As of: Sep 24, 2026 · Record: 0427
  12. PE
    Public Evidence Project: Permit from Pennsylvania DEPAs of: Aug 6, 2026 · Record: source-homer-city-energy-campus-pa
  13. KW

Limitations and interpretation

  • This record is the Kapwork Grow tracker's merged view of a facility, from the tracker snapshot built 2026-09-23. Facts tagged KW are the tracker's resolved values; the per-source rows it was merged from are listed under Sources and on the tracker record.
  • Sources on this record: Compute Atlas: Kubiak, E. (2026). Compute Atlas [Data set]. https://doi.org/10.5281/zenodo.22284476 (CC BY 4.0) · Server Country, https://servercountry.org/data/ (CC BY 4.0) · Public Evidence Project, U.S. Data Center Public Records Dataset, https://publicevidence.org/data/national-data-center-public-records (CC BY 4.0). Every source is licensed for commercial use with attribution.
  • An announced or permitted build is not a contract, an open bid or a purchase order.
  • Capacity figures are as reported by the cited sources and may describe planned rather than energised capacity.

Cite or correct this record

Kapwork Grow, “Homer City Energy Campus”, https://kapwork.com/grow/directory/datacenters/homer-city-energy-campus-pa-dc_70fe86ef54f2, materially updated Sep 24, 2026.

Report an error in this record and we will check it against the cited sources.

An announced or permitted build is not a contract, an open bid or a purchase order. Capacity and dates are as reported by the cited sources. “Not reported” means missing information, not zero. Completed and withdrawn records can remain available as historical records.