MicrosoftEast Point, Fulton County, GAUpdated

Microsoft is building a 324 MW data center in Fulton County, Georgia (under construction). One source reports this facility in the Kapwork Grow tracker.

Capacity
324 MW
Investment
$1.8B ($1.84B)
Building area
700,000 sq ft
Expected completion
2026

Who's on this build

Named in the cited sources. No source reports who builds it.

Schedule

Dates as reported. Not a bid calendar. A planned date is not evidence that work occurred.

  1. this year

    Expected completionPlanned

  2. Today

    Under construction

    Last material change Sep 24, 2026.

  3. 3 yr ago

    Construction start

  4. ~6 yr ago

    Announced

  5. ~6 yr ago

    Reported as announced

    Event date: · First observed: Not reported

Reported updates without an event date

Record quality

Datasets
1
Location
Approximate: city centroid
Summary
From published records
Source as of
Last material change

Site and infrastructure

SC Server CountryKW Kapwork Grow tracker record

Status

Operator
MicrosoftOperator · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0113
Stage
Under constructionStage · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0113
Facility type
HyperscaleFacility type · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 59149995037977

Scale

Reported capacity
324 MWReported capacity · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0113
Reported investment
$1.84BReported investment · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 59149995037977
Reported building area
700,000 sq ftReported building area · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 59149995037977

Reported dates

Announced
2021-02-11Announced · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0113Reported date — see the source for the event evidenced.
Construction start reported
2023Construction start reported · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0113
Expected completion
2026Expected completion · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0113

Site

City
East PointCity · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0113
County
FultonCounty · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0113
State
GeorgiaState · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0113
Location precision
Approximate: city centroidLocation precision · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 59149995037977

Sources, method and limits

Show 1 sourceHide

What each source reports

What each source reports
DatasetReported nameReported statusReported MW
Server CountryMicrosoft - East Point CampusUnder construction324 MW

Sources and evidence

  1. SC
    Server Country project record (CC BY 4.0)As of: Sep 24, 2026 · Record: 0113
  2. KW

Limitations and interpretation

  • This record is the Kapwork Grow tracker's merged view of a facility, from the tracker snapshot built 2026-09-23. Facts tagged KW are the tracker's resolved values; the per-source rows it was merged from are listed under Sources and on the tracker record.
  • Sources on this record: Server Country, https://servercountry.org/data/ (CC BY 4.0). Every source is licensed for commercial use with attribution.
  • An announced or permitted build is not a contract, an open bid or a purchase order.
  • Capacity figures are as reported by the cited sources and may describe planned rather than energised capacity.

Cite or correct this record

Kapwork Grow, “Microsoft - East Point Campus”, https://kapwork.com/grow/directory/datacenters/microsoft-east-point-campus-ga-dc_35cbee715519, materially updated Sep 24, 2026.

Report an error in this record and we will check it against the cited sources.

An announced or permitted build is not a contract, an open bid or a purchase order. Capacity and dates are as reported by the cited sources. “Not reported” means missing information, not zero. Completed and withdrawn records can remain available as historical records.

More builds

Kapwork Grow

Every data center build in the directory, in one place.

Search by company, place or trade.

Browse all builds