NorthMark Strategies Spartanburg High-Performance Computing Center

Valara Holdings (NorthMark Strategies)Spartanburg, Spartanburg County, SCUpdated

Valara Holdings (NorthMark Strategies) is building a 450 MW data center in Spartanburg County, South Carolina (under construction). 2 sources report this facility in the Kapwork Grow tracker.

Capacity
450 MW
Investment
$2.8B
Building area
850,000 sq ft
Expected completion
2026
Reported jobs
27

Who's on this build

Named in the cited sources. No source reports who builds it.

  • Operator

    Valara Holdings (NorthMark Strategies)

Schedule

Dates as reported. Not a bid calendar. A planned date is not evidence that work occurred.

  1. this year

    Expected completionPlanned

  2. Today

    Under construction

    Last material change Sep 24, 2026.

  3. 5 mo ago

    Construction start

  4. 5 mo ago

    Construction start reported

    Event date: · First observed: Not reported

  5. 17 mo ago

    Announced

  6. 17 mo ago

    Reported as announced

    Event date: · First observed: Not reported

Reported updates without an event date

Record quality

Datasets
2, figures differ
Location
Street address reported
Summary
From published records
Source as of
Last material change

Site and infrastructure

CA Compute AtlasSC Server CountryKW Kapwork Grow tracker record

Status

Operator
Valara Holdings (NorthMark Strategies)Operator · Compute AtlasCompute Atlas facility record (Kubiak, E., 2026, CC BY 4.0)As of Sep 13, 2026 · Record: northmark-valara-spartanburg-scOperator · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0448
Stage
Under constructionStage · Compute AtlasCompute Atlas facility record (Kubiak, E., 2026, CC BY 4.0)As of Sep 13, 2026 · Record: northmark-valara-spartanburg-scStage · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0448
Facility type
AI data centerFacility type · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 40058789391289

Scale

Reported capacity
450 MWReported capacity · Compute AtlasCompute Atlas facility record (Kubiak, E., 2026, CC BY 4.0)As of Sep 13, 2026 · Record: northmark-valara-spartanburg-sc
Capacity as the sources range
450 to 457 MWCapacity as the sources range · Compute AtlasCompute Atlas facility record (Kubiak, E., 2026, CC BY 4.0)As of Sep 13, 2026 · Record: northmark-valara-spartanburg-scCapacity as the sources range · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0448
Reported investment
$2.8BReported investment · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 40058789391289
Reported building area
850,000 sq ftReported building area · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 40058789391289
Reported jobs
27Reported jobs · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 40058789391289

Reported dates

Announced
2025-04-22Announced · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0448Reported date — see the source for the event evidenced.
Construction start reported
2026-04-23Construction start reported · Compute AtlasCompute Atlas facility record (Kubiak, E., 2026, CC BY 4.0)As of Sep 13, 2026 · Record: northmark-valara-spartanburg-scReported date — see the source for the event evidenced.
Expected completion
2026Expected completion · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0448

Site

City
SpartanburgCity · Compute AtlasCompute Atlas facility record (Kubiak, E., 2026, CC BY 4.0)As of Sep 13, 2026 · Record: northmark-valara-spartanburg-scCity · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0448
County
SpartanburgCounty · Compute AtlasCompute Atlas facility record (Kubiak, E., 2026, CC BY 4.0)As of Sep 13, 2026 · Record: northmark-valara-spartanburg-scCounty · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0448
State
South CarolinaState · Compute AtlasCompute Atlas facility record (Kubiak, E., 2026, CC BY 4.0)As of Sep 13, 2026 · Record: northmark-valara-spartanburg-scState · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0448
Location precision
Street address reportedLocation precision · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 40058789391289

Power and cooling

Power source
On-site natural gas generationPower source · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 40058789391289
Cooling
EvaporativeCooling · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 40058789391289
AI workload
AI or machine-learning workload reportedAI workload · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 40058789391289

Permits and public records

Incentives reported
Pilot; Property Tax Abatement; Other; $70,000,000Incentives reported · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 40058789391289

Sources, method and limits

Show 6 sourcesHide

What each source reports

What each source reports
DatasetReported nameReported statusReported MW
Compute AtlasNorthMark Strategies Spartanburg High-Performance Computing CenterUnder construction450 MW
Server CountryProject Moc-1 (NorthMark Strategies)Under construction457 MW

Sources and evidence

  1. CA
    Compute Atlas facility record (Kubiak, E., 2026, CC BY 4.0)As of: Sep 13, 2026 · Record: northmark-valara-spartanburg-sc
  2. CA
  3. CA
  4. CA
  5. CA
  6. SC
    Server Country project record (CC BY 4.0)As of: Sep 24, 2026 · Record: 0448
  7. KW

Limitations and interpretation

  • This record is the Kapwork Grow tracker's merged view of a facility, from the tracker snapshot built 2026-09-23. Facts tagged KW are the tracker's resolved values; the per-source rows it was merged from are listed under Sources and on the tracker record.
  • Sources on this record: Compute Atlas: Kubiak, E. (2026). Compute Atlas [Data set]. https://doi.org/10.5281/zenodo.22284476 (CC BY 4.0) · Server Country, https://servercountry.org/data/ (CC BY 4.0). Every source is licensed for commercial use with attribution.
  • An announced or permitted build is not a contract, an open bid or a purchase order.
  • Capacity figures are as reported by the cited sources and may describe planned rather than energised capacity.

Cite or correct this record

Kapwork Grow, “NorthMark Strategies Spartanburg High-Performance Computing Center”, https://kapwork.com/grow/directory/datacenters/northmark-strategies-spartanburg-high-performance-computing-center-sc-dc_246ee9e96bb9, materially updated Sep 24, 2026.

Report an error in this record and we will check it against the cited sources.

An announced or permitted build is not a contract, an open bid or a purchase order. Capacity and dates are as reported by the cited sources. “Not reported” means missing information, not zero. Completed and withdrawn records can remain available as historical records.