Novva Mesa Data Center Campus
Novva is building a 300 MW data center in Maricopa County, Arizona (under construction). 2 sources report this facility in the Kapwork Grow tracker.
- Capacity
- 300 MW
- Investment
- $3B
- Building area
- 1.5M sq ft (1,500,000 sq ft)
- Site
- 160 acres
- Expected completion
- 2026
Who's on this build
Named in the cited sources. No source reports who builds it.
- Other Novva builds
Operator
Novva
Utility
Salt River Project (SRP)
Schedule
Dates as reported. Not a bid calendar. A planned date is not evidence that work occurred.
- this year
Expected completionPlanned
- Today
Under construction
Last material change Sep 24, 2026.
- ~2 yr ago
Construction start
- ~2 yr ago
Announced
Reported updates without an event date
Reported for 2026.
Event date: Not reported · First observed: Not reported
Reported for 2025-01.
Event date: Not reported · First observed: Not reported
Reported for 2025-01.
Event date: Not reported · First observed: Not reported
Record quality
- Datasets
- 2, figures differ
- Location
- Site footprint confirmed
- Summary
- From published records
- Source as of
- Last material change
Site and infrastructure
CA Compute AtlasSC Server CountryKW Kapwork Grow tracker record
Status
- Operator
- Novva
- Stage
- Under construction
- Facility type
- AI data center
Scale
- Reported capacity
- 300 MW
- Reported IT load
- 96 MW
- Reported investment
- $3B
- Reported building area
- 1,500,000 sq ft
- Site area
- 160 acres
- Reported jobs
- 200
Reported dates
- Announced
- 2024-08
- Construction start reported
- 2025-01
- Expected completion
- 2026
Site
- City
- Mesa
- County
- Maricopa
- State
- Arizona
- Location precision
- Site footprint confirmed
Power and cooling
- Utility
- Salt River Project (SRP)
- Power source
- Solar
- Cooling
- Closed loop
- AI workload
- Likely AI or machine-learning workload
Permits and public records
- Incentives reported
- Sales Tax Exemption
Sources, method and limits
Show 7 sourcesHide
What each source reports
| Dataset | Reported name | Reported status | Reported MW |
|---|---|---|---|
| Compute Atlas | Novva Mesa Data Center Campus | Under construction | 300 MW |
| Server Country | Novva Data Centers Mesa Campus | Proposed | 300 MW |
Sources and evidence
- CACompute Atlas facility record (Kubiak, E., 2026, CC BY 4.0)As of: Sep 10, 2026 · Record: novva-mesa-az
- CANovva Data Centers (cited by Compute Atlas)As of: Jul 6, 2026
- CAData Center Dynamics (cited by Compute Atlas)As of: Jul 6, 2026
- CAReport cited by Compute AtlasAs of: Aug 31, 2026
- CAReport cited by Compute AtlasAs of: Aug 31, 2026
- CAPR Newswire / Novva Data Centers (cited by Compute Atlas)As of: Sep 10, 2026
- SCServer Country project record (CC BY 4.0)As of: Sep 24, 2026 · Record: 0021
- KWKapwork Grow tracker record, merged from the sources listed here (free account)As of: Sep 23, 2026 · Record: 229799712065746
Limitations and interpretation
- This record is the Kapwork Grow tracker's merged view of a facility, from the tracker snapshot built 2026-09-23. Facts tagged KW are the tracker's resolved values; the per-source rows it was merged from are listed under Sources and on the tracker record.
- Sources on this record: Compute Atlas: Kubiak, E. (2026). Compute Atlas [Data set]. https://doi.org/10.5281/zenodo.22284476 (CC BY 4.0) · Server Country, https://servercountry.org/data/ (CC BY 4.0). Every source is licensed for commercial use with attribution.
- An announced or permitted build is not a contract, an open bid or a purchase order.
- Capacity figures are as reported by the cited sources and may describe planned rather than energised capacity.
Cite or correct this record
Kapwork Grow, “Novva Mesa Data Center Campus”, https://kapwork.com/grow/directory/datacenters/novva-mesa-data-center-campus-az-dc_d1006a3508d2, materially updated Sep 24, 2026.
Report an error in this record and we will check it against the cited sources.
An announced or permitted build is not a contract, an open bid or a purchase order. Capacity and dates are as reported by the cited sources. “Not reported” means missing information, not zero. Completed and withdrawn records can remain available as historical records.
More builds
Kapwork Grow
Every data center build in the directory, in one place.
Search by company, place or trade.