Data center buildUnder construction

Polaris Technologies Bitcoin Mining Data Center

Polaris Technologies Inc.Muskogee, Muskogee County, OKUpdated

Polaris Technologies Inc. is building a 200 MW data center in Muskogee County, Oklahoma (under construction). One source reports this facility in the Kapwork Grow tracker.

Capacity
200 MW
Investment
$100M
Reported jobs
20

Who's on this build

Named in the cited sources. No source reports who builds it.

  • Operator

    Polaris Technologies Inc.

Schedule

Dates as reported. Not a bid calendar. A planned date is not evidence that work occurred.

  1. Today

    Under construction

    Last material change Sep 24, 2026.

  2. last year

    Expected completionPlanned

  3. ~3 yr ago

    Announced

  4. ~3 yr ago

    Construction start

Reported updates without an event date

Record quality

Datasets
1
Location
Approximate: city centroid
Summary
From published records
Source as of
Last material change

Site and infrastructure

SC Server CountryKW Kapwork Grow tracker record

Status

Operator
Polaris Technologies Inc.Operator · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0405
Stage
Under constructionStage · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0405
Facility type
EnterpriseFacility type · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 209021479677432

Scale

Reported capacity
200 MWReported capacity · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0405
Reported investment
$100MReported investment · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 209021479677432
Reported jobs
20Reported jobs · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 209021479677432

Reported dates

Announced
2024-02Announced · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0405
Construction start reported
2024-02Construction start reported · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0405
Expected completion
2025Expected completion · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0405

Site

City
MuskogeeCity · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0405
County
Muskogee CountyCounty · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0405
State
OklahomaState · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0405
Location precision
Approximate: city centroidLocation precision · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 209021479677432

Sources, method and limits

Show 1 sourceHide

What each source reports

What each source reports
DatasetReported nameReported statusReported MW
Server CountryPolaris Technologies Bitcoin Mining Data CenterUnder construction200 MW

Sources and evidence

  1. SC
    Server Country project record (CC BY 4.0)As of: Sep 24, 2026 · Record: 0405
  2. KW

Limitations and interpretation

  • This record is the Kapwork Grow tracker's merged view of a facility, from the tracker snapshot built 2026-09-23. Facts tagged KW are the tracker's resolved values; the per-source rows it was merged from are listed under Sources and on the tracker record.
  • Sources on this record: Server Country, https://servercountry.org/data/ (CC BY 4.0). Every source is licensed for commercial use with attribution.
  • An announced or permitted build is not a contract, an open bid or a purchase order.
  • Capacity figures are as reported by the cited sources and may describe planned rather than energised capacity.

Cite or correct this record

Kapwork Grow, “Polaris Technologies Bitcoin Mining Data Center”, https://kapwork.com/grow/directory/datacenters/polaris-technologies-bitcoin-mining-data-center-ok-dc_be1a9b0bedf8, materially updated Sep 24, 2026.

Report an error in this record and we will check it against the cited sources.

An announced or permitted build is not a contract, an open bid or a purchase order. Capacity and dates are as reported by the cited sources. “Not reported” means missing information, not zero. Completed and withdrawn records can remain available as historical records.

More builds

Kapwork Grow

Every data center build in the directory, in one place.

Search by company, place or trade.

Browse all builds