Skip to content
Data center buildProposed

Shippingport Power Station and Data Center

Frontier Group of CompaniesShippingport, Beaver County, PAUpdated

Frontier Group of Companies has proposed a 2700 MW data center in Beaver County, Pennsylvania (proposed). One source reports this facility in the Kapwork Grow tracker.

Capacity
2700 MW
Investment
$3.2B
Expected completion
2029
Reported jobs
1,000

Who's on this build

Named in the cited sources. No source reports who builds it.

  • Operator

    Frontier Group of Companies

Schedule

Dates as reported. Not a bid calendar. A planned date is not evidence that work occurred.

  1. in 3 yr

    Expected completionPlanned

  2. Today

    Proposed

    Last material change Sep 24, 2026.

  3. 14 mo ago

    Announced

  4. 14 mo ago

    Reported as announced

    Event date: · First observed: Not reported

  5. last year

    Construction start

Reported updates without an event date

Record quality

Datasets
1
Location
Approximate: city centroid
Summary
From published records
Source as of
Last material change

Site and infrastructure

SC Server CountryKW Kapwork Grow tracker record

Status

Operator
Frontier Group of CompaniesOperator · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0432
Stage
ProposedStage · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0432
Facility type
AI data centerFacility type · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 199375951011778

Scale

Reported capacity
2700 MWReported capacity · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0432
Reported investment
$3.2BReported investment · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 199375951011778
Reported jobs
1,000Reported jobs · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 199375951011778

Reported dates

Announced
2025-07-15Announced · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0432Reported date — see the source for the event evidenced.
Construction start reported
2025Construction start reported · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0432
Expected completion
2029Expected completion · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0432

Site

City
ShippingportCity · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0432
County
Beaver CountyCounty · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0432
State
PennsylvaniaState · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0432
Location precision
Approximate: city centroidLocation precision · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 199375951011778

Power and cooling

AI workload
AI or machine-learning workload reportedAI workload · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 199375951011778

Permits and public records

Incentives reported
Grant; $100,000Incentives reported · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 199375951011778

Sources, method and limits

Show 1 sourceHide

What each source reports

What each source reports
DatasetReported nameReported statusReported MW
Server CountryShippingport Power Station and Data CenterProposed2700 MW

Sources and evidence

  1. SC
    Server Country project record (CC BY 4.0)As of: Sep 24, 2026 · Record: 0432
  2. KW

Limitations and interpretation

  • This record is the Kapwork Grow tracker's merged view of a facility, from the tracker snapshot built 2026-09-23. Facts tagged KW are the tracker's resolved values; the per-source rows it was merged from are listed under Sources and on the tracker record.
  • Sources on this record: Server Country, https://servercountry.org/data/ (CC BY 4.0). Every source is licensed for commercial use with attribution.
  • An announced or permitted build is not a contract, an open bid or a purchase order.
  • Capacity figures are as reported by the cited sources and may describe planned rather than energised capacity.

Cite or correct this record

Kapwork Grow, “Shippingport Power Station and Data Center”, https://kapwork.com/grow/directory/datacenters/shippingport-power-station-and-data-center-pa-dc_b554d4bc9fc2, materially updated Sep 24, 2026.

Report an error in this record and we will check it against the cited sources.

An announced or permitted build is not a contract, an open bid or a purchase order. Capacity and dates are as reported by the cited sources. “Not reported” means missing information, not zero. Completed and withdrawn records can remain available as historical records.