Amazon Web Services is building a 200 MW data center in Umatilla County, Oregon (under construction). One source reports this facility in the Kapwork Grow tracker.

Capacity
200 MW
Investment
$3 ($2.75)
Building area
967,900 sq ft
Expected completion
2026
Reported jobs
70

Who's on this build

Named in the cited sources. No source reports who builds it.

Schedule

Dates as reported. Not a bid calendar. A planned date is not evidence that work occurred.

  1. this year

    Expected completionPlanned

  2. Today

    Under construction

    Last material change Sep 24, 2026.

  3. 2 yr ago

    Construction start

  4. 9 yr ago

    Announced

Reported updates without an event date

Record quality

Datasets
1
Location
Approximate: city centroid
Summary
From published records
Source as of
Last material change

Site and infrastructure

SC Server CountryKW Kapwork Grow tracker record

Status

Operator
Amazon Web ServicesOperator · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0413
Stage
Under constructionStage · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0413
Facility type
HyperscaleFacility type · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 24647759925702

Scale

Reported capacity
200 MWReported capacity · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0413
Reported investment
$2.75Reported investment · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 24647759925702
Reported building area
967,900 sq ftReported building area · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 24647759925702
Reported jobs
70Reported jobs · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 24647759925702

Reported dates

Announced
2017Announced · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0413
Construction start reported
2024Construction start reported · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0413
Expected completion
2026Expected completion · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0413

Site

City
HermistonCity · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0413
County
Umatilla CountyCounty · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0413
State
OregonState · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0413
Location precision
Approximate: city centroidLocation precision · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 24647759925702

Permits and public records

Incentives reported
Property Tax Abatement; OtherIncentives reported · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 24647759925702

Sources, method and limits

Show 1 sourceHide

What each source reports

What each source reports
DatasetReported nameReported statusReported MW
Server CountryAmazon AWS Hermiston Data CentersUnder construction200 MW

Sources and evidence

  1. SC
    Server Country project record (CC BY 4.0)As of: Sep 24, 2026 · Record: 0413
  2. KW

Limitations and interpretation

  • This record is the Kapwork Grow tracker's merged view of a facility, from the tracker snapshot built 2026-09-23. Facts tagged KW are the tracker's resolved values; the per-source rows it was merged from are listed under Sources and on the tracker record.
  • Sources on this record: Server Country, https://servercountry.org/data/ (CC BY 4.0). Every source is licensed for commercial use with attribution.
  • An announced or permitted build is not a contract, an open bid or a purchase order.
  • Capacity figures are as reported by the cited sources and may describe planned rather than energised capacity.

Cite or correct this record

Kapwork Grow, “Amazon AWS Hermiston Data Centers”, https://kapwork.com/grow/directory/datacenters/amazon-aws-hermiston-data-centers-or-dc_166ac0f991c6, materially updated Sep 24, 2026.

Report an error in this record and we will check it against the cited sources.

An announced or permitted build is not a contract, an open bid or a purchase order. Capacity and dates are as reported by the cited sources. “Not reported” means missing information, not zero. Completed and withdrawn records can remain available as historical records.

More builds

Kapwork Grow

Every data center build in the directory, in one place.

Search by company, place or trade.

Browse all builds