Skip to content
Data center buildUnder construction

CoreSite DE3 Denver Data Center

CoreSiteDenver, Denver County, COUpdated

CoreSite is building a 18 MW data center in Denver County, Colorado (under construction). One source reports this facility in the Kapwork Grow tracker.

Capacity
18 MW
Investment
$3 ($2.5)
Building area
170,000 sq ft
Expected completion
2026
IT load
18 MW

Who's on this build

Named in the cited sources. No source reports who builds it.

Schedule

Dates as reported. Not a bid calendar. A planned date is not evidence that work occurred.

  1. this year

    Expected completionPlanned

  2. Today

    Under construction

    Last material change Sep 24, 2026.

  3. 2 yr ago

    Construction start

  4. 3 yr ago

    Announced

Reported updates without an event date

Record quality

Datasets
1
Location
Approximate: city centroid
Summary
From published records
Source as of
Last material change

Site and infrastructure

SC Server CountryKW Kapwork Grow tracker record

Status

Operator
CoreSiteOperator · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0070
Stage
Under constructionStage · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0070
Facility type
AI data centerFacility type · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 37956225289088

Scale

Reported capacity
18 MWReported capacity · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0070
Reported IT load
18 MWReported IT load · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 37956225289088
Reported investment
$2.5Reported investment · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 37956225289088
Reported building area
170,000 sq ftReported building area · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 37956225289088
Reported jobs
75Reported jobs · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 37956225289088

Reported dates

Announced
2023Announced · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0070
Construction start reported
2024Construction start reported · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0070
Expected completion
2026Expected completion · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0070

Site

City
DenverCity · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0070
County
Denver CountyCounty · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0070
State
ColoradoState · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0070
Location precision
Approximate: city centroidLocation precision · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 37956225289088

Power and cooling

AI workload
AI or machine-learning workload reportedAI workload · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 37956225289088

Sources, method and limits

Show 1 sourceHide

What each source reports

What each source reports
DatasetReported nameReported statusReported MW
Server CountryCoreSite DE3 Denver Data CenterUnder construction18 MW

Sources and evidence

  1. SC
    Server Country project record (CC BY 4.0)As of: Sep 24, 2026 · Record: 0070
  2. KW

Limitations and interpretation

  • This record is the Kapwork Grow tracker's merged view of a facility, from the tracker snapshot built 2026-09-23. Facts tagged KW are the tracker's resolved values; the per-source rows it was merged from are listed under Sources and on the tracker record.
  • Sources on this record: Server Country, https://servercountry.org/data/ (CC BY 4.0). Every source is licensed for commercial use with attribution.
  • An announced or permitted build is not a contract, an open bid or a purchase order.
  • Capacity figures are as reported by the cited sources and may describe planned rather than energised capacity.

Cite or correct this record

Kapwork Grow, “CoreSite DE3 Denver Data Center”, https://kapwork.com/grow/directory/datacenters/coresite-de3-denver-data-center-co-dc_22855f534b80, materially updated Sep 24, 2026.

Report an error in this record and we will check it against the cited sources.

An announced or permitted build is not a contract, an open bid or a purchase order. Capacity and dates are as reported by the cited sources. “Not reported” means missing information, not zero. Completed and withdrawn records can remain available as historical records.