Skip to content
Data center buildUnder construction2 of 2 datasets agree

Digi Power X Columbiana AI Data Center

Digi Power XColumbiana, Shelby County, ALUpdated

Digi Power X is building a 40 MW data center in Shelby County, Alabama (under construction). 2 sources report this facility in the Kapwork Grow tracker.

Capacity
40 MW
Investment
$371.5M
Building area
160,000 sq ft
Expected completion
Mar 2027 (2027-03)
Reported jobs
45

Who's on this build

Named in the cited sources. No source reports who builds it.

  • Operator

    Digi Power X

  • Utility

    Alabama Power

Schedule

Dates as reported. Not a bid calendar. A planned date is not evidence that work occurred.

  1. in 6 mo

    Expected completionPlanned

  2. Today

    Under construction

    Last material change Sep 24, 2026.

  3. 4 mo ago

    Announced

  4. 4 mo ago

    Reported as announced

    Event date: · First observed: Not reported

  5. 4 mo ago

    Construction start

Reported updates without an event date

Record quality

Datasets
2, all agree
Location
Street address reported
Summary
From published records
Source as of
Last material change

Site and infrastructure

CA Compute AtlasSC Server CountryKW Kapwork Grow tracker record

Status

Operator
Digi Power XOperator · Compute AtlasCompute Atlas facility record (Kubiak, E., 2026, CC BY 4.0)As of Sep 9, 2026 · Record: digi-power-x-columbiana-alOperator · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0630
Stage
Under constructionStage · Compute AtlasCompute Atlas facility record (Kubiak, E., 2026, CC BY 4.0)As of Sep 9, 2026 · Record: digi-power-x-columbiana-alStage · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0630
Facility type
AI data centerFacility type · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 273560841545631

Scale

Reported capacity
40 MWReported capacity · Compute AtlasCompute Atlas facility record (Kubiak, E., 2026, CC BY 4.0)As of Sep 9, 2026 · Record: digi-power-x-columbiana-alReported capacity · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0630
Reported investment
$371.5MReported investment · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 273560841545631
Reported building area
160,000 sq ftReported building area · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 273560841545631
Reported jobs
45Reported jobs · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 273560841545631

Reported dates

Announced
2026-05-05Announced · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0630Reported date — see the source for the event evidenced.
Construction start reported
2026-05Construction start reported · Compute AtlasCompute Atlas facility record (Kubiak, E., 2026, CC BY 4.0)As of Sep 9, 2026 · Record: digi-power-x-columbiana-al
Expected completion
2027-03Expected completion · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0630

Site

City
ColumbianaCity · Compute AtlasCompute Atlas facility record (Kubiak, E., 2026, CC BY 4.0)As of Sep 9, 2026 · Record: digi-power-x-columbiana-alCity · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0630
County
ShelbyCounty · Compute AtlasCompute Atlas facility record (Kubiak, E., 2026, CC BY 4.0)As of Sep 9, 2026 · Record: digi-power-x-columbiana-alCounty · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0630
State
AlabamaState · Compute AtlasCompute Atlas facility record (Kubiak, E., 2026, CC BY 4.0)As of Sep 9, 2026 · Record: digi-power-x-columbiana-alState · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0630
Location precision
Street address reportedLocation precision · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 273560841545631
Community response
Local opposition reportedCommunity response · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 273560841545631

Power and cooling

Utility
Alabama PowerUtility · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 273560841545631
Power source
Grid powerPower source · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 273560841545631
AI workload
Confirmed AI or machine-learning workloadAI workload · Compute AtlasCompute Atlas facility record (Kubiak, E., 2026, CC BY 4.0)As of Sep 9, 2026 · Record: digi-power-x-columbiana-al

Sources, method and limits

Show 4 sourcesHide

What each source reports

What each source reports
DatasetReported nameReported statusReported MW
Compute AtlasDigi Power X Columbiana AI Data CenterUnder construction40 MW
Server CountryDigi Power X Columbiana AI Data CenterUnder construction40 MW

Sources and evidence

  1. CA
    Compute Atlas facility record (Kubiak, E., 2026, CC BY 4.0)As of: Sep 9, 2026 · Record: digi-power-x-columbiana-al
  2. CA
  3. CA
  4. SC
    Server Country project record (CC BY 4.0)As of: Sep 24, 2026 · Record: 0630
  5. KW

Limitations and interpretation

  • This record is the Kapwork Grow tracker's merged view of a facility, from the tracker snapshot built 2026-09-23. Facts tagged KW are the tracker's resolved values; the per-source rows it was merged from are listed under Sources and on the tracker record.
  • Sources on this record: Compute Atlas: Kubiak, E. (2026). Compute Atlas [Data set]. https://doi.org/10.5281/zenodo.22284476 (CC BY 4.0) · Server Country, https://servercountry.org/data/ (CC BY 4.0). Every source is licensed for commercial use with attribution.
  • An announced or permitted build is not a contract, an open bid or a purchase order.
  • Capacity figures are as reported by the cited sources and may describe planned rather than energised capacity.

Cite or correct this record

Kapwork Grow, “Digi Power X Columbiana AI Data Center”, https://kapwork.com/grow/directory/datacenters/digi-power-x-columbiana-ai-data-center-al-dc_f8cd58c8e79f, materially updated Sep 24, 2026.

Report an error in this record and we will check it against the cited sources.

An announced or permitted build is not a contract, an open bid or a purchase order. Capacity and dates are as reported by the cited sources. “Not reported” means missing information, not zero. Completed and withdrawn records can remain available as historical records.

More builds

Kapwork Grow

Every data center build in the directory, in one place.

Search by company, place or trade.

Browse all builds