Skip to content
Data center buildUnder construction2 datasets report

Google Stillwater Data Center Campus

GoogleStillwater, Payne County, OKUpdated

Google is building a 270 MW data center in Payne County, Oklahoma (under construction). 2 sources report this facility in the Kapwork Grow tracker.

Capacity
270 MW
Investment
$3B
Building area
1.8M sq ft (1,800,000 sq ft)
Site
400 acres
Expected completion
2027

Who's on this build

Named in the cited sources. No source reports who builds it.

Schedule

Dates as reported. Not a bid calendar. A planned date is not evidence that work occurred.

  1. next year

    Expected completionPlanned

  2. Today

    Under construction

    Last material change Sep 24, 2026.

  3. 2 mo ago

    Construction start

  4. 2 mo ago

    Construction start reported

    Event date: · First observed: Not reported

  5. ~1 yr ago

    Announced

Reported updates without an event date

Record quality

Datasets
2, figures differ
Location
Site footprint confirmed
Summary
From published records
Source as of
Last material change

Site and infrastructure

CA Compute AtlasSC Server CountryKW Kapwork Grow tracker record

Status

Operator
GoogleOperator · Compute AtlasCompute Atlas facility record (Kubiak, E., 2026, CC BY 4.0)As of Sep 14, 2026 · Record: google-stillwater-okOperator · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0401
Stage
Under constructionStage · Compute AtlasCompute Atlas facility record (Kubiak, E., 2026, CC BY 4.0)As of Sep 14, 2026 · Record: google-stillwater-okStage · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0401
Facility type
AI data centerFacility type · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 41200647219694

Scale

Reported capacity
270 MWEstimateReported capacity · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 41200647219694
Reported investment
$3BReported investment · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 41200647219694
Reported building area
1,800,000 sq ftReported building area · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 41200647219694
Site area
400 acresSite area · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 41200647219694

Reported dates

Announced
2025-03Announced · Compute AtlasCompute Atlas facility record (Kubiak, E., 2026, CC BY 4.0)As of Sep 14, 2026 · Record: google-stillwater-ok
Construction start reported
2026-07-21Construction start reported · Compute AtlasCompute Atlas facility record (Kubiak, E., 2026, CC BY 4.0)As of Sep 14, 2026 · Record: google-stillwater-okReported date — see the source for the event evidenced.
Expected completion
2027Expected completion · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0401

Site

City
StillwaterCity · Compute AtlasCompute Atlas facility record (Kubiak, E., 2026, CC BY 4.0)As of Sep 14, 2026 · Record: google-stillwater-okCity · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0401
County
PayneCounty · Compute AtlasCompute Atlas facility record (Kubiak, E., 2026, CC BY 4.0)As of Sep 14, 2026 · Record: google-stillwater-okCounty · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0401
State
OklahomaState · Compute AtlasCompute Atlas facility record (Kubiak, E., 2026, CC BY 4.0)As of Sep 14, 2026 · Record: google-stillwater-okState · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0401
Location precision
Site footprint confirmedLocation precision · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 41200647219694
Community response
Local opposition reportedCommunity response · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 41200647219694

Power and cooling

Utility
OG&EUtility · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 41200647219694
Power source
Grid powerPower source · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 41200647219694
AI workload
Confirmed AI or machine-learning workloadAI workload · Compute AtlasCompute Atlas facility record (Kubiak, E., 2026, CC BY 4.0)As of Sep 14, 2026 · Record: google-stillwater-ok

Permits and public records

Incentives reported
25-year ad valorem (property-tax) exemption via a PILOT agreement with Stillwater/Payne County taxing jurisdictions (Stillwater Public Schools, Meridian Technology Center, Payne County, county health dept); PILOT payments rise 1%/yr, estimated ~$58.2M over 25 years for the first two phases (Stillwater / Payne County, OK)Incentives reported · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 41200647219694

Sources, method and limits

Show 9 sourcesHide

What each source reports

What each source reports
DatasetReported nameReported statusReported MW
Compute AtlasGoogle Stillwater Data Center CampusUnder constructionNot reported
Server CountryGoogle Stillwater Data Center CampusUnder constructionNot reported

Sources and evidence

  1. CA
    Compute Atlas facility record (Kubiak, E., 2026, CC BY 4.0)As of: Sep 14, 2026 · Record: google-stillwater-ok
  2. CA
  3. CA
  4. CA
  5. CA
  6. CA
  7. CA
  8. CA
  9. SC
    Server Country project record (CC BY 4.0)As of: Sep 24, 2026 · Record: 0401
  10. KW

Limitations and interpretation

  • This record is the Kapwork Grow tracker's merged view of a facility, from the tracker snapshot built 2026-09-23. Facts tagged KW are the tracker's resolved values; the per-source rows it was merged from are listed under Sources and on the tracker record.
  • Sources on this record: Compute Atlas: Kubiak, E. (2026). Compute Atlas [Data set]. https://doi.org/10.5281/zenodo.22284476 (CC BY 4.0) · Server Country, https://servercountry.org/data/ (CC BY 4.0). Every source is licensed for commercial use with attribution.
  • An announced or permitted build is not a contract, an open bid or a purchase order.
  • Capacity figures are as reported by the cited sources and may describe planned rather than energised capacity.
  • Capacity is estimated by the tracker from reported floor area at 150 W per square foot.

Cite or correct this record

Kapwork Grow, “Google Stillwater Data Center Campus”, https://kapwork.com/grow/directory/datacenters/google-stillwater-data-center-campus-ok-dc_2578c5f129ee, materially updated Sep 24, 2026.

Report an error in this record and we will check it against the cited sources.

An announced or permitted build is not a contract, an open bid or a purchase order. Capacity and dates are as reported by the cited sources. “Not reported” means missing information, not zero. Completed and withdrawn records can remain available as historical records.

More builds

Kapwork Grow

Every data center build in the directory, in one place.

Search by company, place or trade.

Browse all builds