Luckett Road Data Centers (Fremont Peak Properties)
Beale Infrastructure is building a 1500 MW data center in Pima County, Arizona (under construction). 2 sources report this facility in the Kapwork Grow tracker.
- Capacity
- 1500 MW
- Investment
- $5B
- Site
- 661 acres
- Expected completion
- 2029
- Reported jobs
- 180
Who's on this build
Named in the cited sources. No source reports who builds it.
- Other Beale Infrastructure builds
Operator
Beale Infrastructure
Utility
Tucson Electric Power (TEP)
Schedule
Dates as reported. Not a bid calendar. A planned date is not evidence that work occurred.
- in 3 yr
Expected completionPlanned
- Today
Under construction
Last material change Sep 24, 2026.
- 5 mo ago
Construction start
- 8 mo ago
Announced
Reported updates without an event date
Reported for 2029.
Event date: Not reported · First observed: Not reported
Reported for 2026-04.
Event date: Not reported · First observed: Not reported
Reported for 2026-02.
Event date: Not reported · First observed: Not reported
Record quality
- Datasets
- 3, figures differ
- Location
- Site footprint confirmed
- Summary
- From published records
- Source as of
- Last material change
Site and infrastructure
CA Compute AtlasSC Server CountryKW Kapwork Grow tracker record
Status
- Operator
- Beale Infrastructure
- Stage
- Under construction
- Facility type
- AI data center
Scale
- Reported capacity
- 1500 MW
- Capacity as the sources range
- 600 to 1500 MW
- Reported investment
- $5B
- Site area
- 661 acres
- Reported jobs
- 180
Reported dates
- Announced
- 2026-01-06Reported date — see the source for the event evidenced.
- Construction start reported
- 2026-04
- Expected completion
- 2029
Site
- City
- Marana
- County
- Pima
- State
- Arizona
- Location precision
- Site footprint confirmed
- Community response
- Local opposition reported
Power and cooling
- Utility
- Tucson Electric Power (TEP)
- Power source
- Grid power
- Cooling
- Closed loop
- AI workload
- Likely AI or machine-learning workload
Sources, method and limits
Show 16 sourcesHide
What each source reports
| Dataset | Reported name | Reported status | Reported MW |
|---|---|---|---|
| Compute Atlas | Project Blue | Under construction | 600 MW |
| Compute Atlas | Luckett Road Data Centers (Fremont Peak Properties) | Proposed | 1500 MW |
| Server Country | Luckett Road North and South Data Centers | Proposed | 1500 MW |
Sources and evidence
- CACompute Atlas facility record (Kubiak, E., 2026, CC BY 4.0)As of: Sep 10, 2026 · Record: beale-project-blue-pima-county-az
- CAAZ Luminaria (cited by Compute Atlas)As of: Jul 9, 2026
- CAOak Ridge National Laboratory (ORNL) / HIFLD (cited by Compute Atlas)As of: Jul 23, 2026
- CAKOLD News 13 (cited by Compute Atlas)As of: Aug 28, 2026
- CAKJZZ Fronteras Desk (cited by Compute Atlas)As of: Aug 28, 2026
- CAReport cited by Compute AtlasAs of: Aug 31, 2026
- CAPima County, Arizona (cited by Compute Atlas)As of: Sep 10, 2026
- CAConstruction Review Online (cited by Compute Atlas)As of: Sep 10, 2026
- CACompute Atlas facility record (Kubiak, E., 2026, CC BY 4.0)As of: Aug 28, 2026 · Record: fremont-peak-luckett-road-marana-az
- CATucson.com / Arizona Daily Star (cited by Compute Atlas)As of: Jul 9, 2026
- CAAZPM (cited by Compute Atlas)As of: Jul 9, 2026
- CAAZPM (cited by Compute Atlas)As of: Jul 9, 2026
- CATucson Sentinel (cited by Compute Atlas)As of: Jul 9, 2026
- CAKGUN9 (cited by Compute Atlas)As of: Jul 9, 2026
- CAArizona Public Media (AZPM) (cited by Compute Atlas)As of: Aug 28, 2026
- SCServer Country project record (CC BY 4.0)As of: Sep 24, 2026 · Record: 0887
- KWKapwork Grow tracker record, merged from the sources listed here (free account)As of: Sep 23, 2026 · Record: 26376997292877
Limitations and interpretation
- This record is the Kapwork Grow tracker's merged view of a facility, from the tracker snapshot built 2026-09-23. Facts tagged KW are the tracker's resolved values; the per-source rows it was merged from are listed under Sources and on the tracker record.
- Sources on this record: Compute Atlas: Kubiak, E. (2026). Compute Atlas [Data set]. https://doi.org/10.5281/zenodo.22284476 (CC BY 4.0) · Server Country, https://servercountry.org/data/ (CC BY 4.0). Every source is licensed for commercial use with attribution.
- An announced or permitted build is not a contract, an open bid or a purchase order.
- Capacity figures are as reported by the cited sources and may describe planned rather than energised capacity.
Cite or correct this record
Kapwork Grow, “Luckett Road Data Centers (Fremont Peak Properties)”, https://kapwork.com/grow/directory/datacenters/luckett-road-data-centers-fremont-peak-properties-az-dc_17fd5f8dcb4d, materially updated Sep 24, 2026.
Report an error in this record and we will check it against the cited sources.
An announced or permitted build is not a contract, an open bid or a purchase order. Capacity and dates are as reported by the cited sources. “Not reported” means missing information, not zero. Completed and withdrawn records can remain available as historical records.
More builds
Kapwork Grow
Every data center build in the directory, in one place.
Search by company, place or trade.