Nebius Birmingham AI Factory (BHM01)
Nebius is building a 300 MW data center in Jefferson County, Alabama (under construction). 2 sources report this facility in the Kapwork Grow tracker.
- Capacity
- 300 MW
- Investment
- $4 ($3.59)
- Building area
- 500,000 sq ft
- Site
- 80 acres
- Expected completion
- 2028
Who's on this build
Named in the cited sources. No source reports who builds it.
- Other Nebius builds
Operator
Nebius
Utility
Alabama Power
Schedule
Dates as reported. Not a bid calendar. A planned date is not evidence that work occurred.
- in 2 yr
Expected completionPlanned
- Today
Under construction
Last material change Sep 24, 2026.
- 5 mo ago
Construction start
- 5 mo ago
Event date: · First observed: Not reported
- 6 mo ago
Event date: · First observed: Not reported
- 12 mo ago
Announced
Reported updates without an event date
Reported for 2028.
Event date: Not reported · First observed: Not reported
Record quality
- Datasets
- 2, all agree
- Location
- Site footprint confirmed
- Summary
- From published records
- Source as of
- Last material change
Site and infrastructure
CA Compute AtlasSC Server CountryKW Kapwork Grow tracker record
Status
- Operator
- Nebius
- Stage
- Under construction
- Facility type
- AI data center
Scale
- Reported capacity
- 300 MW
- Reported investment
- $3.59
- Reported building area
- 500,000 sq ft
- Site area
- 80 acres
- Reported jobs
- 100
Reported dates
- Announced
- 2025-09-30Reported date — see the source for the event evidenced.
- Construction start reported
- 2026-04-01Reported date — see the source for the event evidenced.
- Expected completion
- 2028
Site
- City
- Birmingham
- County
- Jefferson
- State
- Alabama
- Location precision
- Site footprint confirmed
- Community response
- Local opposition reported
Power and cooling
- Utility
- Alabama Power
- Power source
- Grid power
- Cooling
- Closed loop
- AI workload
- Confirmed AI or machine-learning workload
Sources, method and limits
Show 10 sourcesHide
What each source reports
| Dataset | Reported name | Reported status | Reported MW |
|---|---|---|---|
| Compute Atlas | Nebius Birmingham AI Factory (BHM01) | Under construction | 300 MW |
| Server Country | Nebius Birmingham AI Factory | Under construction | 300 MW |
Sources and evidence
- CACompute Atlas facility record (Kubiak, E., 2026, CC BY 4.0)As of: Sep 9, 2026 · Record: nebius-bhm01-birmingham-al
- CANebius Group (cited by Compute Atlas)As of: Jul 7, 2026
- CAData Center Dynamics (cited by Compute Atlas)As of: Jul 7, 2026
- CANorthwise Project (cited by Compute Atlas)As of: Jul 7, 2026
- CAYellowhammer News (cited by Compute Atlas)As of: Sep 9, 2026
- CABirmingham Watch (cited by Compute Atlas)As of: Jul 7, 2026
- CABaxtel (cited by Compute Atlas)As of: Jul 7, 2026
- CAOak Ridge National Laboratory (ORNL) / HIFLD (cited by Compute Atlas)As of: Jul 23, 2026
- CABirminghamWatch (cited by Compute Atlas)As of: Sep 9, 2026
- SCServer Country project record (CC BY 4.0)As of: Sep 24, 2026 · Record: 0631
- KWKapwork Grow tracker record, merged from the sources listed here (free account)As of: Sep 23, 2026 · Record: 105626064367326
Limitations and interpretation
- This record is the Kapwork Grow tracker's merged view of a facility, from the tracker snapshot built 2026-09-23. Facts tagged KW are the tracker's resolved values; the per-source rows it was merged from are listed under Sources and on the tracker record.
- Sources on this record: Compute Atlas: Kubiak, E. (2026). Compute Atlas [Data set]. https://doi.org/10.5281/zenodo.22284476 (CC BY 4.0) · Server Country, https://servercountry.org/data/ (CC BY 4.0). Every source is licensed for commercial use with attribution.
- An announced or permitted build is not a contract, an open bid or a purchase order.
- Capacity figures are as reported by the cited sources and may describe planned rather than energised capacity.
Cite or correct this record
Kapwork Grow, “Nebius Birmingham AI Factory (BHM01)”, https://kapwork.com/grow/directory/datacenters/nebius-birmingham-ai-factory-bhm01-al-dc_6010fc0baede, materially updated Sep 24, 2026.
Report an error in this record and we will check it against the cited sources.
An announced or permitted build is not a contract, an open bid or a purchase order. Capacity and dates are as reported by the cited sources. “Not reported” means missing information, not zero. Completed and withdrawn records can remain available as historical records.