Skip to content
Data center buildProposed2 of 2 datasets agree

Project Red Wolf

Red Wolf DCD Properties LLCKansas City, Wyandotte County, KSUpdated

Red Wolf DCD Properties LLC has proposed a 600 MW data center in Wyandotte County, Kansas (proposed). 2 sources report this facility in the Kapwork Grow tracker.

Capacity
600 MW
Investment
$12.6B
Building area
1.98M sq ft (1,980,000 sq ft)
Site
400 acres
Reported jobs
60

Who's on this build

Named in the cited sources. No source reports who builds it.

  • Operator

    Red Wolf DCD Properties LLC

Timeline

Dates as reported. Not a bid calendar. A planned date is not evidence that work occurred.

  1. Today

    Proposed

    Last material change Sep 24, 2026.

  2. 17 mo ago

    Announced

Reported updates without an event date

Record quality

Datasets
2, all agree
Location
Site footprint confirmed
Summary
From published records
Source as of
Last material change

Site and infrastructure

CA Compute AtlasSC Server CountryKW Kapwork Grow tracker record

Status

Operator
Red Wolf DCD Properties LLCOperator · Compute AtlasCompute Atlas facility record (Kubiak, E., 2026, CC BY 4.0)As of Jul 18, 2026 · Record: red-wolf-dcd-properties-project-red-wolf-ksOperator · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0193
Stage
ProposedStage · Compute AtlasCompute Atlas facility record (Kubiak, E., 2026, CC BY 4.0)As of Jul 18, 2026 · Record: red-wolf-dcd-properties-project-red-wolf-ksStage · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0193
Facility type
EnterpriseFacility type · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 245759839796661

Scale

Reported capacity
600 MWReported capacity · Compute AtlasCompute Atlas facility record (Kubiak, E., 2026, CC BY 4.0)As of Jul 18, 2026 · Record: red-wolf-dcd-properties-project-red-wolf-ksReported capacity · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0193
Reported investment
$12.6BReported investment · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 245759839796661
Reported building area
1,980,000 sq ftReported building area · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 245759839796661
Site area
400 acresSite area · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 245759839796661
Reported jobs
60Reported jobs · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 245759839796661

Reported dates

Announced
2025-04Announced · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0193

Site

City
Kansas CityCity · Compute AtlasCompute Atlas facility record (Kubiak, E., 2026, CC BY 4.0)As of Jul 18, 2026 · Record: red-wolf-dcd-properties-project-red-wolf-ksCity · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0193
County
WyandotteCounty · Compute AtlasCompute Atlas facility record (Kubiak, E., 2026, CC BY 4.0)As of Jul 18, 2026 · Record: red-wolf-dcd-properties-project-red-wolf-ksCounty · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0193
State
KansasState · Compute AtlasCompute Atlas facility record (Kubiak, E., 2026, CC BY 4.0)As of Jul 18, 2026 · Record: red-wolf-dcd-properties-project-red-wolf-ksState · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0193
Location precision
Site footprint confirmedLocation precision · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 245759839796661
Community response
Local opposition reportedCommunity response · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 245759839796661

Permits and public records

Incentives reported
Sales Tax ExemptionIncentives reported · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 245759839796661

Sources, method and limits

Show 6 sourcesHide

What each source reports

What each source reports
DatasetReported nameReported statusReported MW
Compute AtlasProject Red WolfProposed600 MW
Server CountryRed Wolf DCD Properties Data Center CampusProposed600 MW

Sources and evidence

  1. CA
    Compute Atlas facility record (Kubiak, E., 2026, CC BY 4.0)As of: Jul 18, 2026 · Record: red-wolf-dcd-properties-project-red-wolf-ks
  2. CA
  3. CA
  4. CA
  5. CA
  6. SC
    Server Country project record (CC BY 4.0)As of: Sep 24, 2026 · Record: 0193
  7. KW

Limitations and interpretation

  • This record is the Kapwork Grow tracker's merged view of a facility, from the tracker snapshot built 2026-09-23. Facts tagged KW are the tracker's resolved values; the per-source rows it was merged from are listed under Sources and on the tracker record.
  • Sources on this record: Compute Atlas: Kubiak, E. (2026). Compute Atlas [Data set]. https://doi.org/10.5281/zenodo.22284476 (CC BY 4.0) · Server Country, https://servercountry.org/data/ (CC BY 4.0). Every source is licensed for commercial use with attribution.
  • An announced or permitted build is not a contract, an open bid or a purchase order.
  • Capacity figures are as reported by the cited sources and may describe planned rather than energised capacity.

Cite or correct this record

Kapwork Grow, “Project Red Wolf”, https://kapwork.com/grow/directory/datacenters/project-red-wolf-ks-dc_df846bf37db5, materially updated Sep 24, 2026.

Report an error in this record and we will check it against the cited sources.

An announced or permitted build is not a contract, an open bid or a purchase order. Capacity and dates are as reported by the cited sources. “Not reported” means missing information, not zero. Completed and withdrawn records can remain available as historical records.