Data center buildApproved2 datasets report

QTS Project Blue Hole

QTSBlakely, Early County, GAUpdated

QTS has approval for a 1000 MW data center in Early County, Georgia (approved). 2 sources report this facility in the Kapwork Grow tracker.

Capacity
1000 MW
Investment
$7
Building area
1 sq ft
Expected completion
2035

Who's on this build

Named in the cited sources. No source reports who builds it.

Schedule

Dates as reported. Not a bid calendar. A planned date is not evidence that work occurred.

  1. in 9 yr

    Expected completionPlanned

  2. Today

    Approved

    Last material change Sep 24, 2026.

  3. 6 mo ago

    Announced

  4. 6 mo ago

    Reported as announced

    Event date: · First observed: Not reported

Reported updates without an event date

Record quality

Datasets
2, figures differ
Location
Site footprint confirmed
Summary
From published records
Source as of
Last material change

Site and infrastructure

CA Compute AtlasSC Server CountryKW Kapwork Grow tracker record

Status

Operator
QTSOperator · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 70258062773421
Stage
ApprovedStage · Compute AtlasCompute Atlas facility record (Kubiak, E., 2026, CC BY 4.0)As of Jul 26, 2026 · Record: qts-blue-hole-blakely-ga
Facility type
AI data centerFacility type · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 70258062773421

Scale

Reported capacity
1000 MWReported capacity · Compute AtlasCompute Atlas facility record (Kubiak, E., 2026, CC BY 4.0)As of Jul 26, 2026 · Record: qts-blue-hole-blakely-ga
Capacity as the sources range
1000 to 1400 MWCapacity as the sources range · Compute AtlasCompute Atlas facility record (Kubiak, E., 2026, CC BY 4.0)As of Jul 26, 2026 · Record: qts-blue-hole-blakely-gaCapacity as the sources range · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0671
Reported investment
$7Reported investment · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 70258062773421
Reported building area
1 sq ftReported building area · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 70258062773421

Reported dates

Announced
2026-03-10Announced · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0671Reported date — see the source for the event evidenced.
Expected completion
2035Expected completion · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0671

Site

City
BlakelyCity · Compute AtlasCompute Atlas facility record (Kubiak, E., 2026, CC BY 4.0)As of Jul 26, 2026 · Record: qts-blue-hole-blakely-gaCity · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0671
County
EarlyCounty · Compute AtlasCompute Atlas facility record (Kubiak, E., 2026, CC BY 4.0)As of Jul 26, 2026 · Record: qts-blue-hole-blakely-gaCounty · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0671
State
GeorgiaState · Compute AtlasCompute Atlas facility record (Kubiak, E., 2026, CC BY 4.0)As of Jul 26, 2026 · Record: qts-blue-hole-blakely-gaState · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0671
Location precision
Site footprint confirmedLocation precision · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 70258062773421

Power and cooling

Power source
Grid powerPower source · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 70258062773421
AI workload
Likely AI or machine-learning workloadAI workload · Compute AtlasCompute Atlas facility record (Kubiak, E., 2026, CC BY 4.0)As of Jul 26, 2026 · Record: qts-blue-hole-blakely-ga

Sources, method and limits

Show 4 sourcesHide

What each source reports

What each source reports
DatasetReported nameReported statusReported MW
Compute AtlasQTS Project Blue HoleApproved1000 MW
Server CountryQTS - BlakelyProposed1400 MW

Sources and evidence

  1. CA
    Compute Atlas facility record (Kubiak, E., 2026, CC BY 4.0)As of: Jul 26, 2026 · Record: qts-blue-hole-blakely-ga
  2. CA
  3. CA
  4. SC
    Server Country project record (CC BY 4.0)As of: Sep 24, 2026 · Record: 0671
  5. KW

Limitations and interpretation

  • This record is the Kapwork Grow tracker's merged view of a facility, from the tracker snapshot built 2026-09-23. Facts tagged KW are the tracker's resolved values; the per-source rows it was merged from are listed under Sources and on the tracker record.
  • Sources on this record: Compute Atlas: Kubiak, E. (2026). Compute Atlas [Data set]. https://doi.org/10.5281/zenodo.22284476 (CC BY 4.0) · Server Country, https://servercountry.org/data/ (CC BY 4.0). Every source is licensed for commercial use with attribution.
  • An announced or permitted build is not a contract, an open bid or a purchase order.
  • Capacity figures are as reported by the cited sources and may describe planned rather than energised capacity.

Cite or correct this record

Kapwork Grow, “QTS Project Blue Hole”, https://kapwork.com/grow/directory/datacenters/qts-project-blue-hole-ga-dc_3fe63adfccad, materially updated Sep 24, 2026.

Report an error in this record and we will check it against the cited sources.

An announced or permitted build is not a contract, an open bid or a purchase order. Capacity and dates are as reported by the cited sources. “Not reported” means missing information, not zero. Completed and withdrawn records can remain available as historical records.