Data center buildUnder construction

Tract South Valley Technology Park

Fleet Data CentersReno/Sparks, Storey County, NVUpdated

Fleet Data Centers is building a 1215 MW data center in Storey County, Nevada (under construction). One source reports this facility in the Kapwork Grow tracker.

Capacity
1215 MW
Investment
$5 ($4.6)
Building area
2 sq ft
Expected completion
Sep 2027 (2027-09)
IT load
200 MW

Who's on this build

Named in the cited sources. No source reports who builds it.

Schedule

Dates as reported. Not a bid calendar. A planned date is not evidence that work occurred.

  1. in 12 mo

    Expected completionPlanned

  2. Today

    Under construction

    Last material change Sep 24, 2026.

  3. 4 mo ago

    Construction start

  4. ~3 yr ago

    Announced

Reported updates without an event date

Record quality

Datasets
1
Summary
From published records
Source as of
Last material change

Site and infrastructure

SC Server CountryKW Kapwork Grow tracker record

Status

Operator
Fleet Data CentersOperator · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0309
Tenants
Unnamed AA- investment-grade tenantTenants · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 267887421647755
Stage
Under constructionStage · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0309
Facility type
AI data centerFacility type · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 267887421647755

Scale

Reported capacity
1215 MWReported capacity · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0309
Reported IT load
200 MWReported IT load · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 267887421647755
Reported investment
$4.6Reported investment · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 267887421647755
Reported building area
2 sq ftReported building area · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 267887421647755
Reported jobs
100Reported jobs · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 267887421647755

Reported dates

Announced
2023-10Announced · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0309
Construction start reported
2026-05Construction start reported · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0309
Expected completion
2027-09Expected completion · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0309

Site

City
Reno/SparksCity · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0309
County
Storey CountyCounty · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0309
State
NevadaState · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0309

Power and cooling

AI workload
AI or machine-learning workload reportedAI workload · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 267887421647755

Permits and public records

Incentives reported
Sales Tax Exemption; Property Tax Abatement; $23,350,806Incentives reported · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 267887421647755

Sources, method and limits

Show 1 sourceHide

What each source reports

What each source reports
DatasetReported nameReported statusReported MW
Server CountryTract South Valley Technology ParkUnder construction1215 MW

Sources and evidence

  1. SC
    Server Country project record (CC BY 4.0)As of: Sep 24, 2026 · Record: 0309
  2. KW

Limitations and interpretation

  • This record is the Kapwork Grow tracker's merged view of a facility, from the tracker snapshot built 2026-09-23. Facts tagged KW are the tracker's resolved values; the per-source rows it was merged from are listed under Sources and on the tracker record.
  • Sources on this record: Server Country, https://servercountry.org/data/ (CC BY 4.0). Every source is licensed for commercial use with attribution.
  • An announced or permitted build is not a contract, an open bid or a purchase order.
  • Capacity figures are as reported by the cited sources and may describe planned rather than energised capacity.

Cite or correct this record

Kapwork Grow, “Tract South Valley Technology Park”, https://kapwork.com/grow/directory/datacenters/tract-south-valley-technology-park-nv-dc_f3a4669b6b8b, materially updated Sep 24, 2026.

Report an error in this record and we will check it against the cited sources.

An announced or permitted build is not a contract, an open bid or a purchase order. Capacity and dates are as reported by the cited sources. “Not reported” means missing information, not zero. Completed and withdrawn records can remain available as historical records.