PowerHouse Charlotte Campus
PowerHouse Data Centers is building a 300 MW data center in Mecklenburg County, North Carolina (under construction). 2 sources report this facility in the Kapwork Grow tracker.
- Capacity
- 300 MW
- Investment
- $3.5B
- Building area
- 1.5M sq ft (1,500,000 sq ft)
- Site
- 120 acres
- Expected completion
- 2027
Who's on this build
Named in the cited sources. No source reports who builds it.
- Other PowerHouse Data Centers builds
Operator
PowerHouse Data Centers
Utility
Duke Energy Carolinas
Schedule
Dates as reported. Not a bid calendar. A planned date is not evidence that work occurred.
- next year
Expected completionPlanned
- this year
Construction start
- Today
Under construction
Last material change Sep 24, 2026.
- 2 yr ago
Announced
Reported updates without an event date
Reported for 2027.
Event date: Not reported · First observed: Not reported
Reported for 2026.
Event date: Not reported · First observed: Not reported
Reported for 2024.
Event date: Not reported · First observed: Not reported
Record quality
- Datasets
- 2, all agree
- Location
- Site footprint confirmed
- Summary
- From published records
- Source as of
- Last material change
Site and infrastructure
CA Compute AtlasSC Server CountryKW Kapwork Grow tracker record
Status
- Operator
- PowerHouse Data Centers
- Stage
- Under construction
- Facility type
- AI data center
Scale
- Reported capacity
- 300 MW
- Reported investment
- $3.5B
- Reported building area
- 1,500,000 sq ft
- Site area
- 120 acres
Reported dates
- Announced
- 2024
- Construction start reported
- 2026
- Expected completion
- 2027
Site
- City
- Charlotte
- County
- Mecklenburg
- State
- North Carolina
- Location precision
- Site footprint confirmed
- Community response
- Local opposition reported
Power and cooling
- Utility
- Duke Energy Carolinas
- Power source
- Grid power
- AI workload
- Likely AI or machine-learning workload
Sources, method and limits
Show 5 sourcesHide
What each source reports
| Dataset | Reported name | Reported status | Reported MW |
|---|---|---|---|
| Compute Atlas | PowerHouse Charlotte Campus | Under construction | 300 MW |
| Server Country | PowerHouse Data Centers Charlotte Campus | Under construction | 300 MW |
Sources and evidence
- CACompute Atlas facility record (Kubiak, E., 2026, CC BY 4.0)As of: Sep 10, 2026 · Record: powerhouse-charlotte-nc
- CAData Center Dynamics (cited by Compute Atlas)As of: Jul 7, 2026
- CAOak Ridge National Laboratory (ORNL) / HIFLD (cited by Compute Atlas)As of: Jul 23, 2026
- CAReport cited by Compute AtlasAs of: Sep 10, 2026
- SCServer Country project record (CC BY 4.0)As of: Sep 24, 2026 · Record: 0372
- KWKapwork Grow tracker record, merged from the sources listed here (free account)As of: Sep 23, 2026 · Record: 33405056430596
Limitations and interpretation
- This record is the Kapwork Grow tracker's merged view of a facility, from the tracker snapshot built 2026-09-23. Facts tagged KW are the tracker's resolved values; the per-source rows it was merged from are listed under Sources and on the tracker record.
- Sources on this record: Compute Atlas: Kubiak, E. (2026). Compute Atlas [Data set]. https://doi.org/10.5281/zenodo.22284476 (CC BY 4.0) · Server Country, https://servercountry.org/data/ (CC BY 4.0). Every source is licensed for commercial use with attribution.
- An announced or permitted build is not a contract, an open bid or a purchase order.
- Capacity figures are as reported by the cited sources and may describe planned rather than energised capacity.
Cite or correct this record
Kapwork Grow, “PowerHouse Charlotte Campus”, https://kapwork.com/grow/directory/datacenters/powerhouse-charlotte-campus-nc-dc_1e61b885b204, materially updated Sep 24, 2026.
Report an error in this record and we will check it against the cited sources.
An announced or permitted build is not a contract, an open bid or a purchase order. Capacity and dates are as reported by the cited sources. “Not reported” means missing information, not zero. Completed and withdrawn records can remain available as historical records.
More builds
- Amazon Web Services (AWS) Richmond County CampusNorth Carolina
- Amazon Web Services Richmond County Data Center CampusNorth Carolina
- American Tower Reedy Creek Data Center (East Charlotte)North Carolina
- Compass Statesville CampusNorth Carolina
- Deep River Data AI Data Center (Cumnock, Lee County)North Carolina
Kapwork Grow
Every data center build in the directory, in one place.
Search by company, place or trade.