Carrollton Industrial Campus
PowerHouse Data Centers has proposed a 800 MW data center in Carroll County, Kentucky (proposed). One source reports this facility in the Kapwork Grow tracker.
- Capacity
- 800 MW
- Investment
- $9.6B
- Site
- 500 acres
- Reported jobs
- 320
Who's on this build
Named in the cited sources. No source reports who builds it.
- Other PowerHouse Data Centers builds
Operator
PowerHouse Data Centers
Utility
Kentucky Utilities Company
Record quality
- Datasets
- 1
- Location
- Street address reported
- Summary
- From published records
- Source as of
- Last material change
Site and infrastructure
CA Compute AtlasKW Kapwork Grow tracker record
Status
- Operator
- PowerHouse Data Centers
- Stage
- Proposed
- Facility type
- Enterprise
Scale
- Reported capacity
- 800 MW
- Reported investment
- $9.6B
- Site area
- 500 acres
- Reported jobs
- 320
Site
- City
- Carrollton
- County
- Carroll
- State
- Kentucky
- Location precision
- Street address reported
- Community response
- Local opposition reported
Power and cooling
- Utility
- Kentucky Utilities Company
- Power source
- Grid power
Sources, method and limits
Show 5 sourcesHide
What each source reports
| Dataset | Reported name | Reported status | Reported MW |
|---|---|---|---|
| Compute Atlas | Carrollton Industrial Campus | Proposed | 800 MW |
Sources and evidence
- CACompute Atlas facility record (Kubiak, E., 2026, CC BY 4.0)As of: Sep 15, 2026 · Record: powerhouse-poe-carrollton-industrial-campus-carroll-county-ky
- CAReport cited by Compute AtlasAs of: Sep 10, 2026
- CAWAVE3 (cited by Compute Atlas)As of: Sep 10, 2026
- CALouisville Public Media (cited by Compute Atlas)As of: Sep 10, 2026
- CALouisville Business First (via Yahoo News) (cited by Compute Atlas)As of: Sep 15, 2026
- KWKapwork Grow tracker record, merged from the sources listed here (free account)As of: Sep 23, 2026 · Record: 120575944677823
Limitations and interpretation
- This record is the Kapwork Grow tracker's merged view of a facility, from the tracker snapshot built 2026-09-23. Facts tagged KW are the tracker's resolved values; the per-source rows it was merged from are listed under Sources and on the tracker record.
- Sources on this record: Compute Atlas: Kubiak, E. (2026). Compute Atlas [Data set]. https://doi.org/10.5281/zenodo.22284476 (CC BY 4.0). Every source is licensed for commercial use with attribution.
- An announced or permitted build is not a contract, an open bid or a purchase order.
- Capacity figures are as reported by the cited sources and may describe planned rather than energised capacity.
Cite or correct this record
Kapwork Grow, “Carrollton Industrial Campus”, https://kapwork.com/grow/directory/datacenters/carrollton-industrial-campus-ky-dc_6da9c659d9bf, materially updated Sep 24, 2026.
Report an error in this record and we will check it against the cited sources.
An announced or permitted build is not a contract, an open bid or a purchase order. Capacity and dates are as reported by the cited sources. “Not reported” means missing information, not zero. Completed and withdrawn records can remain available as historical records.