QTS Aurora-Denver Data Center Campus (DEN1)
QTS is building a 177 MW data center in Arapahoe County, Colorado (under construction). 3 sources report this facility in the Kapwork Grow tracker.
- Capacity
- 177 MW
- Investment
- $1B
- Site
- 67 acres
- IT load
- 160 MW
- Reported jobs
- 70
Who's on this build
Named in the cited sources. No source reports who builds it.
- Other QTS builds
Operator
QTS
Utility
Xcel Energy (Public Service Company of Colorado)
Timeline
Dates as reported. Not a bid calendar. A planned date is not evidence that work occurred.
- Today
Under construction
Last material change Sep 24, 2026.
- ~3 yr ago
Construction start
- ~4 yr ago
Announced
Reported updates without an event date
Reported for 2024-03.
Event date: Not reported · First observed: Not reported
Reported for 2024-01.
Event date: Not reported · First observed: Not reported
Reported for 2023.
Event date: Not reported · First observed: Not reported
Record quality
- Datasets
- 3, figures differ
- Location
- Site footprint confirmed
- Summary
- From published records
- Source as of
- Last material change
Site and infrastructure
CA Compute AtlasSC Server CountryEPA EPA facility registryKW Kapwork Grow tracker record
Status
- Operator
- QTS
- Stage
- Under construction
- Facility type
- AI data center
Scale
- Reported capacity
- 177 MW
- Reported IT load
- 160 MW
- Reported investment
- $1B
- Site area
- 67 acres
- Reported jobs
- 70
Reported dates
- Announced
- 2022-05
- Construction start reported
- 2024-01
Site
- City
- Aurora
- County
- Arapahoe
- State
- Colorado
- Location precision
- Site footprint confirmed
Power and cooling
- Utility
- Xcel Energy (Public Service Company of Colorado)
- Power source
- Grid power
- AI workload
- Likely AI or machine-learning workload
Permits and public records
- EPA air permit
- Major Emissions
- EPA compliance status
- No Violation Identified
- Incentives reported
- Sales Tax Exemption; Property Tax Abatement; Other
Sources, method and limits
Show 6 sourcesHide
What each source reports
| Dataset | Reported name | Reported status | Reported MW |
|---|---|---|---|
| Compute Atlas | QTS Aurora-Denver Data Center Campus (DEN1) | Under construction | 177 MW |
| Server Country | QTS Aurora-Denver Data Center | Under construction | 177 MW |
| EPA ECHO | QTS Aurora LLC - QTS DEN1 | Operating | Not reported |
Sources and evidence
- CACompute Atlas facility record (Kubiak, E., 2026, CC BY 4.0)As of: Jul 8, 2026 · Record: qts-aurora-co
- CAData Center Dynamics (cited by Compute Atlas)As of: Jul 6, 2026
- CAMile High CRE (cited by Compute Atlas)As of: Jul 6, 2026
- CAColorado Public Radio (cited by Compute Atlas)As of: Jul 8, 2026
- SCServer Country project record (CC BY 4.0)As of: Sep 24, 2026 · Record: 0069
- EPAEPA Facility Registry (ECHO) record (US government, public domain)As of: Sep 24, 2026 · Record: 110071767620
- KWKapwork Grow tracker record, merged from the sources listed here (free account)As of: Sep 23, 2026 · Record: 47842002575465
Limitations and interpretation
- This record is the Kapwork Grow tracker's merged view of a facility, from the tracker snapshot built 2026-09-23. Facts tagged KW are the tracker's resolved values; the per-source rows it was merged from are listed under Sources and on the tracker record.
- Sources on this record: Compute Atlas: Kubiak, E. (2026). Compute Atlas [Data set]. https://doi.org/10.5281/zenodo.22284476 (CC BY 4.0) · Server Country, https://servercountry.org/data/ (CC BY 4.0) · US EPA Facility Registry Service via ECHO (public domain). Every source is licensed for commercial use with attribution.
- An announced or permitted build is not a contract, an open bid or a purchase order.
- Capacity figures are as reported by the cited sources and may describe planned rather than energised capacity.
Cite or correct this record
Kapwork Grow, “QTS Aurora-Denver Data Center Campus (DEN1)”, https://kapwork.com/grow/directory/datacenters/qts-aurora-denver-data-center-campus-den1-co-dc_2b831591a069, materially updated Sep 24, 2026.
Report an error in this record and we will check it against the cited sources.
An announced or permitted build is not a contract, an open bid or a purchase order. Capacity and dates are as reported by the cited sources. “Not reported” means missing information, not zero. Completed and withdrawn records can remain available as historical records.