Shippingport Industrial Park
Aligned is building a 2000 MW data center in Beaver County, Pennsylvania (under construction). One source reports this facility in the Kapwork Grow tracker.
- Capacity
- 2000 MW
- Investment
- $10B
- Site
- 660 acres
- Reported jobs
- 640
Who's on this build
Named in the cited sources. No source reports who builds it.
- Other Aligned builds
Operator
Aligned
Timeline
Dates as reported. Not a bid calendar. A planned date is not evidence that work occurred.
- Today
Under construction
Last material change Sep 24, 2026.
- 16 days ago
Construction start
- 16 days ago
Event date: · First observed: Not reported
Reported updates without an event date
Reported for 2026.
Event date: Not reported · First observed: Not reported
Record quality
- Datasets
- 1
- Location
- Street address reported
- Summary
- From published records
- Source as of
- Last material change
Site and infrastructure
CA Compute AtlasKW Kapwork Grow tracker record
Status
- Operator
- Aligned
- Stage
- Under construction
- Facility type
- Enterprise
Scale
- Reported capacity
- 2000 MW
- Reported investment
- $10B
- Site area
- 660 acres
- Reported jobs
- 640
Reported dates
- Construction start reported
- 2026-09-12Reported date — see the source for the event evidenced.
Site
- City
- Shippingport
- County
- Beaver
- State
- Pennsylvania
- Location precision
- Street address reported
Power and cooling
- Power source
- On-site natural gas generation
- Cooling
- Closed loop
Sources, method and limits
Show 8 sourcesHide
What each source reports
| Dataset | Reported name | Reported status | Reported MW |
|---|---|---|---|
| Compute Atlas | Shippingport Industrial Park | Under construction | 2000 MW |
Sources and evidence
- CACompute Atlas facility record (Kubiak, E., 2026, CC BY 4.0)As of: Sep 12, 2026 · Record: aligned-shippingport-pa
- CAData Center Dynamics (cited by Compute Atlas)As of: Jul 17, 2026
- CABeaver County Business (cited by Compute Atlas)As of: Aug 17, 2026
- CACBS Pittsburgh (cited by Compute Atlas)As of: Aug 19, 2026
- CA
- CA
- CAAligned Data Centers (GlobeNewswire) (cited by Compute Atlas)As of: Sep 12, 2026
- CAMarcellus Drilling News (cited by Compute Atlas)As of: Sep 12, 2026
- KWKapwork Grow tracker record, merged from the sources listed here (free account)As of: Sep 23, 2026 · Record: 37260413448813
Limitations and interpretation
- This record is the Kapwork Grow tracker's merged view of a facility, from the tracker snapshot built 2026-09-23. Facts tagged KW are the tracker's resolved values; the per-source rows it was merged from are listed under Sources and on the tracker record.
- Sources on this record: Compute Atlas: Kubiak, E. (2026). Compute Atlas [Data set]. https://doi.org/10.5281/zenodo.22284476 (CC BY 4.0). Every source is licensed for commercial use with attribution.
- An announced or permitted build is not a contract, an open bid or a purchase order.
- Capacity figures are as reported by the cited sources and may describe planned rather than energised capacity.
Cite or correct this record
Kapwork Grow, “Shippingport Industrial Park”, https://kapwork.com/grow/directory/datacenters/shippingport-industrial-park-pa-dc_21e35db5326d, materially updated Sep 24, 2026.
Report an error in this record and we will check it against the cited sources.
An announced or permitted build is not a contract, an open bid or a purchase order. Capacity and dates are as reported by the cited sources. “Not reported” means missing information, not zero. Completed and withdrawn records can remain available as historical records.
More builds
- 1205 Commonwealth Dr. Data Center (former Pennhurst Asylum)Pennsylvania
- 2100 Renaissance Blvd. Data Center (MLP Ventures)Pennsylvania
- 216 Greenfield Road (Chirisa Technology Parks)Pennsylvania
- 2201, 2301, 2501, 2701, & 2901 Renaissance Blvd. Data Center (MLP Ventures)Pennsylvania
- 3200 Horizon Dr. Data Center (MLP Ventures)Pennsylvania
Kapwork Grow
Every data center build in the directory, in one place.
Search by company, place or trade.