T5 @ Chicago III (Northlake)

T5Northlake, Cook County, ILUpdated

T5 is building a 36 MW data center in Cook County, Illinois (under construction). 2 sources report this facility in the Kapwork Grow tracker.

Capacity
36 MW
Investment
$500M
Building area
250,000 sq ft
Expected completion
2027
IT load
36 MW

Who's on this build

Named in the cited sources. No source reports who builds it.

Schedule

Dates as reported. Not a bid calendar. A planned date is not evidence that work occurred.

  1. next year

    Expected completionPlanned

  2. Today

    Under construction

    Last material change Sep 24, 2026.

  3. 28 days ago

    Construction start

  4. 28 days ago

    Construction start reported

    Event date: · First observed: Not reported

  5. ~2 yr ago

    Construction start reported

    Event date: · First observed: Not reported

  6. 3 yr ago

    Announced

Reported updates without an event date

Record quality

Datasets
2, all agree
Location
Street address reported
Summary
From published records
Source as of
Last material change

Site and infrastructure

CA Compute AtlasSC Server CountryKW Kapwork Grow tracker record

Status

Operator
T5Operator · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 270008901110521
Tenants
Undisclosed pre-leased userTenants · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 270008901110521
Stage
Under constructionStage · Compute AtlasCompute Atlas facility record (Kubiak, E., 2026, CC BY 4.0)As of Sep 12, 2026 · Record: t5-chicago-iii-northlake-ilStage · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0155
Facility type
EnterpriseFacility type · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 270008901110521

Scale

Reported capacity
36 MWReported capacity · Compute AtlasCompute Atlas facility record (Kubiak, E., 2026, CC BY 4.0)As of Sep 12, 2026 · Record: t5-chicago-iii-northlake-ilReported capacity · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0155
Reported IT load
36 MWReported IT load · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 270008901110521
Reported investment
$500MReported investment · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 270008901110521
Reported building area
250,000 sq ftReported building area · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 270008901110521
Reported jobs
20Reported jobs · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 270008901110521

Reported dates

Announced
2023Announced · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0155
Construction start reported
2026-08-31Construction start reported · Compute AtlasCompute Atlas facility record (Kubiak, E., 2026, CC BY 4.0)As of Sep 12, 2026 · Record: t5-chicago-iii-northlake-ilReported date — see the source for the event evidenced.
Expected completion
2027Expected completion · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0155

Site

City
NorthlakeCity · Compute AtlasCompute Atlas facility record (Kubiak, E., 2026, CC BY 4.0)As of Sep 12, 2026 · Record: t5-chicago-iii-northlake-ilCity · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0155
County
CookCounty · Compute AtlasCompute Atlas facility record (Kubiak, E., 2026, CC BY 4.0)As of Sep 12, 2026 · Record: t5-chicago-iii-northlake-ilCounty · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0155
State
IllinoisState · Compute AtlasCompute Atlas facility record (Kubiak, E., 2026, CC BY 4.0)As of Sep 12, 2026 · Record: t5-chicago-iii-northlake-ilState · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0155
Location precision
Street address reportedLocation precision · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 270008901110521

Permits and public records

Incentives reported
Illinois Data Center Investment Program (sales/use tax exemption MOU) (Illinois) $15,750,000Incentives reported · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 270008901110521

Sources, method and limits

Show 4 sourcesHide

What each source reports

What each source reports
DatasetReported nameReported statusReported MW
Compute AtlasT5 @ Chicago III (Northlake)Under construction36 MW
Server CountryT5 Chicago III - NorthlakeUnder construction36 MW

Sources and evidence

  1. CA
    Compute Atlas facility record (Kubiak, E., 2026, CC BY 4.0)As of: Sep 12, 2026 · Record: t5-chicago-iii-northlake-il
  2. CA
  3. CA
  4. SC
    Server Country project record (CC BY 4.0)As of: Sep 24, 2026 · Record: 0155
  5. KW

Limitations and interpretation

  • This record is the Kapwork Grow tracker's merged view of a facility, from the tracker snapshot built 2026-09-23. Facts tagged KW are the tracker's resolved values; the per-source rows it was merged from are listed under Sources and on the tracker record.
  • Sources on this record: Compute Atlas: Kubiak, E. (2026). Compute Atlas [Data set]. https://doi.org/10.5281/zenodo.22284476 (CC BY 4.0) · Server Country, https://servercountry.org/data/ (CC BY 4.0). Every source is licensed for commercial use with attribution.
  • An announced or permitted build is not a contract, an open bid or a purchase order.
  • Capacity figures are as reported by the cited sources and may describe planned rather than energised capacity.

Cite or correct this record

Kapwork Grow, “T5 @ Chicago III (Northlake)”, https://kapwork.com/grow/directory/datacenters/t5-chicago-iii-northlake-il-dc_f59258a30af9, materially updated Sep 24, 2026.

Report an error in this record and we will check it against the cited sources.

An announced or permitted build is not a contract, an open bid or a purchase order. Capacity and dates are as reported by the cited sources. “Not reported” means missing information, not zero. Completed and withdrawn records can remain available as historical records.