Applied Digital Polaris Forge 2
Applied Digital is building a 280 MW data center in Cass County, North Dakota (under construction). 2 sources report this facility in the Kapwork Grow tracker.
- Capacity
- 280 MW
- Investment
- $3B
- Building area
- 1.81M sq ft (1,814,000 sq ft)
- Site
- 900 acres
- Expected completion
- 2027
Who's on this build
Named in the cited sources. No source reports who builds it.
- Other Applied Digital builds
Operator
Applied Digital
Utility
Cass County Electric Cooperative / Minnkota Power Cooperative
Schedule
Dates as reported. Not a bid calendar. A planned date is not evidence that work occurred.
- next year
Expected completionPlanned
- Today
Under construction
Last material change Sep 24, 2026.
- 12 mo ago
Construction start
- 13 mo ago
Announced
- 13 mo ago
Event date: · First observed: Not reported
Reported updates without an event date
Reported for 2027.
Event date: Not reported · First observed: Not reported
Reported for 2025-09.
Event date: Not reported · First observed: Not reported
Record quality
- Datasets
- 2, figures differ
- Location
- Site footprint confirmed
- Summary
- From published records
- Source as of
- Last material change
Site and infrastructure
CA Compute AtlasSC Server CountryKW Kapwork Grow tracker record
Status
- Operator
- Applied Digital
- Tenants
- Oracle
- Stage
- Under construction
- Facility type
- AI data center
Scale
- Reported capacity
- 280 MW
- Capacity as the sources range
- 280 to 300 MW
- Reported IT load
- 200 MW
- Reported investment
- $3B
- Reported building area
- 1,814,000 sq ft
- Site area
- 900 acres
- Reported jobs
- 200
Reported dates
- Announced
- 2025-08-18Reported date — see the source for the event evidenced.
- Construction start reported
- 2025-09
- Expected completion
- 2027
Site
- City
- Harwood
- County
- Cass
- State
- North Dakota
- Location precision
- Site footprint confirmed
- Community response
- Local opposition reported
Power and cooling
- Utility
- Cass County Electric Cooperative / Minnkota Power Cooperative
- Power source
- Grid power
- AI workload
- Confirmed AI or machine-learning workload
Permits and public records
- Incentives reported
- Sales Tax Exemption
Sources, method and limits
Show 6 sourcesHide
What each source reports
| Dataset | Reported name | Reported status | Reported MW |
|---|---|---|---|
| Compute Atlas | Applied Digital Polaris Forge 2 | Under construction | 280 MW |
| Server Country | Applied Digital Polaris Forge 2 | Under construction | 300 MW |
Sources and evidence
- CACompute Atlas facility record (Kubiak, E., 2026, CC BY 4.0)As of: Sep 10, 2026 · Record: applied-digital-polaris-forge-2-harwood-nd
- CAApplied Digital Corporation (cited by Compute Atlas)As of: Jul 6, 2026
- CAMinnkota Power Cooperative (cited by Compute Atlas)As of: Jul 6, 2026
- CAInForum (cited by Compute Atlas)As of: Sep 10, 2026
- CAValley News Live (cited by Compute Atlas)As of: Sep 10, 2026
- SCServer Country project record (CC BY 4.0)As of: Sep 24, 2026 · Record: 0381
- KWKapwork Grow tracker record, merged from the sources listed here (free account)As of: Sep 23, 2026 · Record: 14576097981257
Limitations and interpretation
- This record is the Kapwork Grow tracker's merged view of a facility, from the tracker snapshot built 2026-09-23. Facts tagged KW are the tracker's resolved values; the per-source rows it was merged from are listed under Sources and on the tracker record.
- Sources on this record: Compute Atlas: Kubiak, E. (2026). Compute Atlas [Data set]. https://doi.org/10.5281/zenodo.22284476 (CC BY 4.0) · Server Country, https://servercountry.org/data/ (CC BY 4.0). Every source is licensed for commercial use with attribution.
- An announced or permitted build is not a contract, an open bid or a purchase order.
- Capacity figures are as reported by the cited sources and may describe planned rather than energised capacity.
Cite or correct this record
Kapwork Grow, “Applied Digital Polaris Forge 2”, https://kapwork.com/grow/directory/datacenters/applied-digital-polaris-forge-2-nd-dc_0d41c3247349, materially updated Sep 24, 2026.
Report an error in this record and we will check it against the cited sources.
An announced or permitted build is not a contract, an open bid or a purchase order. Capacity and dates are as reported by the cited sources. “Not reported” means missing information, not zero. Completed and withdrawn records can remain available as historical records.