AWS New Albany (Beech/Miller Road Campus)
Amazon Web Services is building a data center in Licking County, Ohio (under construction). One source reports this facility in the Kapwork Grow tracker.
- Investment
- $3.5B
- Site
- 458 acres
Who's on this build
Named in the cited sources. No source reports who builds it.
- Other Amazon Web Services builds
Operator
Amazon Web Services
Timeline
Dates as reported. Not a bid calendar. A planned date is not evidence that work occurred.
- Today
Under construction
Last material change Sep 24, 2026.
- ~3 yr ago
Announced
- ~3 yr ago
Construction start
Reported updates without an event date
Reported for 2024.
Event date: Not reported · First observed: Not reported
Reported for 2023-09.
Event date: Not reported · First observed: Not reported
Reported for 2023-09.
Event date: Not reported · First observed: Not reported
Record quality
- Datasets
- 3, figures differ
- Location
- Site footprint confirmed
- Summary
- From published records
- Source as of
- Last material change
Site and infrastructure
CA Compute AtlasKW Kapwork Grow tracker record
Status
- Operator
- Amazon Web Services
- Stage
- Under construction
- Facility type
- AI data center
Scale
- Reported investment
- $3.5B
- Site area
- 458 acres
Reported dates
- Announced
- 2023-09
- Construction start reported
- 2023-09
Site
- City
- New Albany
- County
- Licking
- State
- Ohio
- Location precision
- Site footprint confirmed
Power and cooling
- Power source
- Grid power
- AI workload
- Likely AI or machine-learning workload
Permits and public records
- Incentives reported
- New Albany data-center property-tax abatement (100% for 15 years, then 75% for 15 years) (City of New Albany / Community Reinvestment Area)
Sources, method and limits
Show 13 sourcesHide
What each source reports
| Dataset | Reported name | Reported status | Reported MW |
|---|---|---|---|
| Compute Atlas | AWS New Albany (2550 Beech Road) | Operating | Not reported |
| Compute Atlas | AWS New Albany (Beech/Miller Road Campus) | Under construction | Not reported |
| Compute Atlas | AWS New Albany (Newton Court) | Operating | Not reported |
Sources and evidence
- CACompute Atlas facility record (Kubiak, E., 2026, CC BY 4.0)As of: Jul 18, 2026 · Record: aws-2550-beech-road-new-albany-oh
- CALicking County Auditor GIS / Assessor (cited by Compute Atlas)As of: Jul 18, 2026
- CACity of New Albany (cited by Compute Atlas)As of: Jul 18, 2026
- CABaxtel (cited by Compute Atlas)As of: Jul 18, 2026
- CACompute Atlas facility record (Kubiak, E., 2026, CC BY 4.0)As of: Jul 18, 2026 · Record: aws-beech-road-new-albany-oh
- CALicking County Auditor GIS / Assessor (cited by Compute Atlas)As of: Jul 18, 2026
- CACity of New Albany (cited by Compute Atlas)As of: Jul 18, 2026
- CACity of New Albany (cited by Compute Atlas)As of: Jul 18, 2026
- CAData Center Frontier (cited by Compute Atlas)As of: Jul 18, 2026
- CACompute Atlas facility record (Kubiak, E., 2026, CC BY 4.0)As of: Jul 24, 2026 · Record: aws-newton-court-new-albany-oh
- CALicking County Auditor GIS / Assessor (cited by Compute Atlas)As of: Jul 19, 2026
- CABaxtel (cited by Compute Atlas)As of: Jul 19, 2026
- CAReport cited by Compute AtlasAs of: Jul 24, 2026
- KWKapwork Grow tracker record, merged from the sources listed here (free account)As of: Sep 23, 2026 · Record: 234444412537089
Limitations and interpretation
- This record is the Kapwork Grow tracker's merged view of a facility, from the tracker snapshot built 2026-09-23. Facts tagged KW are the tracker's resolved values; the per-source rows it was merged from are listed under Sources and on the tracker record.
- Sources on this record: Compute Atlas: Kubiak, E. (2026). Compute Atlas [Data set]. https://doi.org/10.5281/zenodo.22284476 (CC BY 4.0). Every source is licensed for commercial use with attribution.
- An announced or permitted build is not a contract, an open bid or a purchase order.
- Capacity figures are as reported by the cited sources and may describe planned rather than energised capacity.
Cite or correct this record
Kapwork Grow, “AWS New Albany (Beech/Miller Road Campus)”, https://kapwork.com/grow/directory/datacenters/aws-new-albany-beech-miller-road-campus-oh-dc_d539d7edc901, materially updated Sep 24, 2026.
Report an error in this record and we will check it against the cited sources.
An announced or permitted build is not a contract, an open bid or a purchase order. Capacity and dates are as reported by the cited sources. “Not reported” means missing information, not zero. Completed and withdrawn records can remain available as historical records.