Data center buildProposed

EdgeConneX - Elk Grove Village 2025 Data Center

EdgeConneXElk Grove Village, Cook County, ILUpdated

EdgeConneX has proposed a 23 MW data center in Cook County, Illinois (proposed). One source reports this facility in the Kapwork Grow tracker.

Capacity
23 MW
Investment
$501.2M ($501.24M)
Building area
86,046 sq ft
Expected completion
2026

Who's on this build

Named in the cited sources. No source reports who builds it.

Schedule

Dates as reported. Not a bid calendar. A planned date is not evidence that work occurred.

  1. this year

    Expected completionPlanned

  2. Today

    Proposed

    Last material change Sep 24, 2026.

  3. last year

    Announced

Reported updates without an event date

Record quality

Datasets
1
Location
Approximate: city centroid
Summary
From published records
Source as of
Last material change

Site and infrastructure

SC Server CountryKW Kapwork Grow tracker record

Status

Operator
EdgeConneXOperator · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0919
Stage
ProposedStage · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0919
Facility type
AI data centerFacility type · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 229952432086601

Scale

Reported capacity
23 MWReported capacity · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0919
Reported investment
$501.24MReported investment · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 229952432086601
Reported building area
86,046 sq ftReported building area · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 229952432086601

Reported dates

Announced
2025Announced · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0919
Expected completion
2026Expected completion · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0919

Site

City
Elk Grove VillageCity · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0919
County
Cook CountyCounty · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0919
State
IllinoisState · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0919
Location precision
Approximate: city centroidLocation precision · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 229952432086601

Power and cooling

AI workload
AI or machine-learning workload reportedAI workload · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 229952432086601

Sources, method and limits

Show 1 sourceHide

What each source reports

What each source reports
DatasetReported nameReported statusReported MW
Server CountryEdgeConneX - Elk Grove Village 2025 Data CenterProposed23 MW

Sources and evidence

  1. SC
    Server Country project record (CC BY 4.0)As of: Sep 24, 2026 · Record: 0919
  2. KW

Limitations and interpretation

  • This record is the Kapwork Grow tracker's merged view of a facility, from the tracker snapshot built 2026-09-23. Facts tagged KW are the tracker's resolved values; the per-source rows it was merged from are listed under Sources and on the tracker record.
  • Sources on this record: Server Country, https://servercountry.org/data/ (CC BY 4.0). Every source is licensed for commercial use with attribution.
  • An announced or permitted build is not a contract, an open bid or a purchase order.
  • Capacity figures are as reported by the cited sources and may describe planned rather than energised capacity.

Cite or correct this record

Kapwork Grow, “EdgeConneX - Elk Grove Village 2025 Data Center”, https://kapwork.com/grow/directory/datacenters/edgeconnex-elk-grove-village-2025-data-center-il-dc_d123f9079e49, materially updated Sep 24, 2026.

Report an error in this record and we will check it against the cited sources.

An announced or permitted build is not a contract, an open bid or a purchase order. Capacity and dates are as reported by the cited sources. “Not reported” means missing information, not zero. Completed and withdrawn records can remain available as historical records.