Meta Kuna Data Center
Meta is building a 60 MW data center in Ada County, Idaho (under construction). 2 sources report this facility in the Kapwork Grow tracker.
- Capacity
- 60 MW
- Investment
- $800M
- Building area
- 960,000 sq ft
- Site
- 485 acres
- IT load
- 60 MW
Who's on this build
Named in the cited sources. No source reports who builds it.
- Other Meta builds
Operator
Meta
Utility
Idaho Power
Schedule
Dates as reported. Not a bid calendar. A planned date is not evidence that work occurred.
- Today
Under construction
Last material change Sep 24, 2026.
- last year
Expected completionPlanned
- ~4 yr ago
Construction start
- ~5 yr ago
Announced
Reported updates without an event date
Reported for 2025.
Event date: Not reported · First observed: Not reported
Reported for 2023-10.
Event date: Not reported · First observed: Not reported
Reported for 2022-09.
Event date: Not reported · First observed: Not reported
Record quality
- Datasets
- 2, figures differ
- Location
- Site footprint confirmed
- Summary
- From published records
- Source as of
- Last material change
Site and infrastructure
CA Compute AtlasSC Server CountryKW Kapwork Grow tracker record
Status
- Operator
- Meta
- Stage
- Under construction
- Facility type
- AI data center
Scale
- Reported capacity
- 60 MW
- Reported IT load
- 60 MW
- Reported investment
- $800M
- Reported building area
- 960,000 sq ft
- Site area
- 485 acres
- Reported jobs
- 100
Reported dates
- Announced
- 2022-02-16Reported date — see the source for the event evidenced.
- Construction start reported
- 2022-09
- Expected completion
- 2025
Site
- City
- Kuna
- County
- Ada
- State
- Idaho
- Location precision
- Site footprint confirmed
Power and cooling
- Utility
- Idaho Power
- Power source
- Mixed sources
- AI workload
- Confirmed AI or machine-learning workload
Permits and public records
- Incentives reported
- Sales Tax Exemption
Sources, method and limits
Show 7 sourcesHide
What each source reports
| Dataset | Reported name | Reported status | Reported MW |
|---|---|---|---|
| Compute Atlas | Meta Kuna Data Center | Under construction | Not reported |
| Server Country | Meta Kuna Data Center | Under construction | 60 MW |
Sources and evidence
- CACompute Atlas facility record (Kubiak, E., 2026, CC BY 4.0)As of: Aug 8, 2026 · Record: meta-kuna-id
- CAData Center Dynamics (cited by Compute Atlas)As of: Jul 6, 2026
- CAConstruction Equipment Guide (cited by Compute Atlas)As of: Jul 6, 2026
- CAIdaho Business Review (cited by Compute Atlas)As of: Jul 6, 2026
- CAOak Ridge National Laboratory (ORNL) / HIFLD (cited by Compute Atlas)As of: Jul 23, 2026
- CADeseret News (cited by Compute Atlas)As of: Aug 8, 2026
- SCServer Country project record (CC BY 4.0)As of: Sep 24, 2026 · Record: 0133
- KWKapwork Grow tracker record, merged from the sources listed here (free account)As of: Sep 23, 2026 · Record: 211484454379332
Limitations and interpretation
- This record is the Kapwork Grow tracker's merged view of a facility, from the tracker snapshot built 2026-09-23. Facts tagged KW are the tracker's resolved values; the per-source rows it was merged from are listed under Sources and on the tracker record.
- Sources on this record: Compute Atlas: Kubiak, E. (2026). Compute Atlas [Data set]. https://doi.org/10.5281/zenodo.22284476 (CC BY 4.0) · Server Country, https://servercountry.org/data/ (CC BY 4.0). Every source is licensed for commercial use with attribution.
- An announced or permitted build is not a contract, an open bid or a purchase order.
- Capacity figures are as reported by the cited sources and may describe planned rather than energised capacity.
Cite or correct this record
Kapwork Grow, “Meta Kuna Data Center”, https://kapwork.com/grow/directory/datacenters/meta-kuna-data-center-id-dc_c0580fc75f44, materially updated Sep 24, 2026.
Report an error in this record and we will check it against the cited sources.
An announced or permitted build is not a contract, an open bid or a purchase order. Capacity and dates are as reported by the cited sources. “Not reported” means missing information, not zero. Completed and withdrawn records can remain available as historical records.