Data center buildUnder construction

Rowan Cinco Data Center

RowanLytle area, Medina County, TXUpdated

Rowan is building a 300 MW data center in Medina County, Texas (under construction). One source reports this facility in the Kapwork Grow tracker.

Capacity
300 MW
Investment
$550M
Expected completion
2027

Who's on this build

Named in the cited sources. No source reports who builds it.

Schedule

Dates as reported. Not a bid calendar. A planned date is not evidence that work occurred.

  1. next year

    Expected completionPlanned

  2. Today

    Under construction

    Last material change Sep 24, 2026.

  3. 7 mo ago

    Announced

  4. 7 mo ago

    Reported as announced

    Event date: · First observed: Not reported

Reported updates without an event date

Record quality

Datasets
1
Summary
From published records
Source as of
Last material change

Site and infrastructure

SC Server CountryKW Kapwork Grow tracker record

Status

Operator
RowanOperator · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 1019
Stage
Under constructionStage · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 1019
Facility type
AI data centerFacility type · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 168577960530951

Scale

Reported capacity
300 MWReported capacity · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 1019
Reported investment
$550MReported investment · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 168577960530951

Reported dates

Announced
2026-02-11Announced · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 1019Reported date — see the source for the event evidenced.
Expected completion
2027Expected completion · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 1019

Site

City
Lytle areaCity · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 1019
County
Medina CountyCounty · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 1019
State
TexasState · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 1019

Power and cooling

AI workload
AI or machine-learning workload reportedAI workload · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 168577960530951

Sources, method and limits

Show 1 sourceHide

What each source reports

What each source reports
DatasetReported nameReported statusReported MW
Server CountryRowan Cinco Data CenterUnder construction300 MW

Sources and evidence

  1. SC
    Server Country project record (CC BY 4.0)As of: Sep 24, 2026 · Record: 1019
  2. KW

Limitations and interpretation

  • This record is the Kapwork Grow tracker's merged view of a facility, from the tracker snapshot built 2026-09-23. Facts tagged KW are the tracker's resolved values; the per-source rows it was merged from are listed under Sources and on the tracker record.
  • Sources on this record: Server Country, https://servercountry.org/data/ (CC BY 4.0). Every source is licensed for commercial use with attribution.
  • An announced or permitted build is not a contract, an open bid or a purchase order.
  • Capacity figures are as reported by the cited sources and may describe planned rather than energised capacity.

Cite or correct this record

Kapwork Grow, “Rowan Cinco Data Center”, https://kapwork.com/grow/directory/datacenters/rowan-cinco-data-center-tx-dc_99521d745407, materially updated Sep 24, 2026.

Report an error in this record and we will check it against the cited sources.

An announced or permitted build is not a contract, an open bid or a purchase order. Capacity and dates are as reported by the cited sources. “Not reported” means missing information, not zero. Completed and withdrawn records can remain available as historical records.