Aligned is building a 96 MW data center in Erie County, Ohio (under construction). One source reports this facility in the Kapwork Grow tracker.

Capacity
96 MW
Investment
$202M
Building area
200,000 sq ft
Expected completion
2026
Reported jobs
18

Who's on this build

Named in the cited sources. No source reports who builds it.

Schedule

Dates as reported. Not a bid calendar. A planned date is not evidence that work occurred.

  1. this year

    Expected completionPlanned

  2. Today

    Under construction

    Last material change Sep 24, 2026.

  3. ~2 yr ago

    Construction start

  4. ~3 yr ago

    Announced

Reported updates without an event date

Record quality

Datasets
1
Summary
From published records
Source as of
Last material change

Site and infrastructure

SC Server CountryKW Kapwork Grow tracker record

Status

Operator
AlignedOperator · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0398
Stage
Under constructionStage · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0398
Facility type
AI data centerFacility type · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 192463242787638

Scale

Reported capacity
96 MWReported capacity · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0398
Reported investment
$202MReported investment · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 192463242787638
Reported building area
200,000 sq ftReported building area · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 192463242787638
Reported jobs
18Reported jobs · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 192463242787638

Reported dates

Announced
2023-09Announced · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0398
Construction start reported
2024-05Construction start reported · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0398
Expected completion
2026Expected completion · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0398

Site

City
Perkins Township (Sandusky area)City · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0398
County
Erie CountyCounty · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0398
State
OhioState · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0398

Power and cooling

AI workload
AI or machine-learning workload reportedAI workload · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 192463242787638

Permits and public records

Incentives reported
Tif; Property Tax Abatement; Sales Tax Exemption; $10,200,000Incentives reported · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 192463242787638

Sources, method and limits

Show 1 sourceHide

What each source reports

What each source reports
DatasetReported nameReported statusReported MW
Server CountryAligned NEO-01 CampusUnder construction96 MW

Sources and evidence

  1. SC
    Server Country project record (CC BY 4.0)As of: Sep 24, 2026 · Record: 0398
  2. KW

Limitations and interpretation

  • This record is the Kapwork Grow tracker's merged view of a facility, from the tracker snapshot built 2026-09-23. Facts tagged KW are the tracker's resolved values; the per-source rows it was merged from are listed under Sources and on the tracker record.
  • Sources on this record: Server Country, https://servercountry.org/data/ (CC BY 4.0). Every source is licensed for commercial use with attribution.
  • An announced or permitted build is not a contract, an open bid or a purchase order.
  • Capacity figures are as reported by the cited sources and may describe planned rather than energised capacity.

Cite or correct this record

Kapwork Grow, “Aligned NEO-01 Campus”, https://kapwork.com/grow/directory/datacenters/aligned-neo-01-campus-oh-dc_af0b5737fb36, materially updated Sep 24, 2026.

Report an error in this record and we will check it against the cited sources.

An announced or permitted build is not a contract, an open bid or a purchase order. Capacity and dates are as reported by the cited sources. “Not reported” means missing information, not zero. Completed and withdrawn records can remain available as historical records.

More builds

Kapwork Grow

Every data center build in the directory, in one place.

Search by company, place or trade.

Browse all builds