Data center buildProposed2 of 2 datasets agree

Bitdeer Shalersville Data Center Campus

BitdeerShalersville Township, Portage County, OHUpdated

Bitdeer has proposed a 750 MW data center in Portage County, Ohio (proposed). 2 sources report this facility in the Kapwork Grow tracker.

Capacity
750 MW
Investment
$300M
Building area
793,500 sq ft
Site
257 acres
Reported jobs
200

Who's on this build

Named in the cited sources. No source reports who builds it.

Timeline

Dates as reported. Not a bid calendar. A planned date is not evidence that work occurred.

  1. Today

    Proposed

    Last material change Sep 24, 2026.

  2. 4 mo ago

    Announced

  3. 4 mo ago

    Reported as announced

    Event date: · First observed: Not reported

Reported updates without an event date

Record quality

Datasets
2, all agree
Location
Street address reported
Summary
From published records
Source as of
Last material change

Site and infrastructure

CA Compute AtlasSC Server CountryKW Kapwork Grow tracker record

Status

Operator
BitdeerOperator · Compute AtlasCompute Atlas facility record (Kubiak, E., 2026, CC BY 4.0)As of Jul 23, 2026 · Record: bitdeer-shalersville-portage-county-ohOperator · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0785
Stage
ProposedStage · Compute AtlasCompute Atlas facility record (Kubiak, E., 2026, CC BY 4.0)As of Jul 23, 2026 · Record: bitdeer-shalersville-portage-county-ohStage · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0785
Facility type
AI data centerFacility type · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 21281794417401

Scale

Reported capacity
750 MWReported capacity · Compute AtlasCompute Atlas facility record (Kubiak, E., 2026, CC BY 4.0)As of Jul 23, 2026 · Record: bitdeer-shalersville-portage-county-ohReported capacity · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0785
Reported investment
$300MReported investment · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 21281794417401
Reported building area
793,500 sq ftReported building area · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 21281794417401
Site area
257 acresSite area · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 21281794417401
Reported jobs
200Reported jobs · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 21281794417401

Reported dates

Announced
2026-05-27Announced · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0785Reported date — see the source for the event evidenced.

Site

City
Shalersville TownshipCity · Compute AtlasCompute Atlas facility record (Kubiak, E., 2026, CC BY 4.0)As of Jul 23, 2026 · Record: bitdeer-shalersville-portage-county-ohCity · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0785
County
PortageCounty · Compute AtlasCompute Atlas facility record (Kubiak, E., 2026, CC BY 4.0)As of Jul 23, 2026 · Record: bitdeer-shalersville-portage-county-ohCounty · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0785
State
OhioState · Compute AtlasCompute Atlas facility record (Kubiak, E., 2026, CC BY 4.0)As of Jul 23, 2026 · Record: bitdeer-shalersville-portage-county-ohState · Server CountryServer Country project record (CC BY 4.0)As of Sep 24, 2026 · Record: 0785
Location precision
Street address reportedLocation precision · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 21281794417401
Community response
Local opposition reportedCommunity response · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 21281794417401

Power and cooling

Utility
Ohio Edison (FirstEnergy)Utility · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 21281794417401
Power source
Grid powerPower source · Kapwork Grow tracker recordKapwork Grow tracker record, merged from the sources listed here (free account)As of Sep 23, 2026 · Record: 21281794417401
AI workload
Likely AI or machine-learning workloadAI workload · Compute AtlasCompute Atlas facility record (Kubiak, E., 2026, CC BY 4.0)As of Jul 23, 2026 · Record: bitdeer-shalersville-portage-county-oh

Sources, method and limits

Show 7 sourcesHide

What each source reports

What each source reports
DatasetReported nameReported statusReported MW
Compute AtlasBitdeer Shalersville Data Center CampusProposed750 MW
Server CountryBitdeer Shalersville Data Center CampusProposed750 MW

Sources and evidence

  1. CA
    Compute Atlas facility record (Kubiak, E., 2026, CC BY 4.0)As of: Jul 23, 2026 · Record: bitdeer-shalersville-portage-county-oh
  2. CA
  3. CA
  4. CA
  5. CA
  6. CA
  7. SC
    Server Country project record (CC BY 4.0)As of: Sep 24, 2026 · Record: 0785
  8. KW

Limitations and interpretation

  • This record is the Kapwork Grow tracker's merged view of a facility, from the tracker snapshot built 2026-09-23. Facts tagged KW are the tracker's resolved values; the per-source rows it was merged from are listed under Sources and on the tracker record.
  • Sources on this record: Compute Atlas: Kubiak, E. (2026). Compute Atlas [Data set]. https://doi.org/10.5281/zenodo.22284476 (CC BY 4.0) · Server Country, https://servercountry.org/data/ (CC BY 4.0). Every source is licensed for commercial use with attribution.
  • An announced or permitted build is not a contract, an open bid or a purchase order.
  • Capacity figures are as reported by the cited sources and may describe planned rather than energised capacity.

Cite or correct this record

Kapwork Grow, “Bitdeer Shalersville Data Center Campus”, https://kapwork.com/grow/directory/datacenters/bitdeer-shalersville-data-center-campus-oh-dc_135b0dcbe2f9, materially updated Sep 24, 2026.

Report an error in this record and we will check it against the cited sources.

An announced or permitted build is not a contract, an open bid or a purchase order. Capacity and dates are as reported by the cited sources. “Not reported” means missing information, not zero. Completed and withdrawn records can remain available as historical records.

More builds

Kapwork Grow

Every data center build in the directory, in one place.

Search by company, place or trade.

Browse all builds