Meta Jeffersonville Data Center
Meta is building a 407 MW data center in Clark County, Indiana (under construction). 2 sources report this facility in the Kapwork Grow tracker.
- Capacity
- 407 MW
- Investment
- $800M
- Building area
- 700,000 sq ft
- Site
- 619 acres
- Expected completion
- 2026
Who's on this build
Named in the cited sources. No source reports who builds it.
- Other Meta builds
Operator
Meta
Utility
Duke Energy Indiana
Schedule
Dates as reported. Not a bid calendar. A planned date is not evidence that work occurred.
- this year
Expected completionPlanned
- Today
Under construction
Last material change Sep 24, 2026.
- ~3 yr ago
Announced
- ~3 yr ago
Event date: · First observed: Not reported
- ~3 yr ago
Construction start
Reported updates without an event date
Reported for 2026.
Event date: Not reported · First observed: Not reported
Reported for 2024-01.
Event date: Not reported · First observed: Not reported
Record quality
- Datasets
- 2, figures differ
- Location
- Site footprint confirmed
- Summary
- From published records
- Source as of
- Last material change
Site and infrastructure
CA Compute AtlasSC Server CountryKW Kapwork Grow tracker record
Status
- Operator
- Meta
- Tenants
- Meta Platforms
- Stage
- Under construction
- Facility type
- AI data center
Scale
- Reported capacity
- 407 MW
- Capacity as the sources range
- 225 to 407 MW
- Reported investment
- $800M
- Reported building area
- 700,000 sq ft
- Site area
- 619 acres
- Reported jobs
- 100
Reported dates
- Announced
- 2024-01-25Reported date — see the source for the event evidenced.
- Construction start reported
- 2024-01
- Expected completion
- 2026
Site
- City
- Jeffersonville
- County
- Clark
- State
- Indiana
- Location precision
- Site footprint confirmed
- Community response
- Local opposition reported
Power and cooling
- Utility
- Duke Energy Indiana
- Power source
- Solar
- Cooling
- Closed loop
- AI workload
- Confirmed AI or machine-learning workload
Permits and public records
- Incentives reported
- 35-year sales tax exemption (Indiana (IEDC))
Sources, method and limits
Show 7 sourcesHide
What each source reports
| Dataset | Reported name | Reported status | Reported MW |
|---|---|---|---|
| Compute Atlas | Meta Jeffersonville Data Center | Under construction | 407 MW |
| Server Country | Meta Jeffersonville Data Center | Under construction | 225 MW |
Sources and evidence
- CACompute Atlas facility record (Kubiak, E., 2026, CC BY 4.0)As of: Aug 5, 2026 · Record: meta-jeffersonville-in
- CAMeta Data Centers (cited by Compute Atlas)As of: Jul 6, 2026
- CABloomberg (cited by Compute Atlas)As of: Jul 6, 2026
- CAWAVE 3 News (cited by Compute Atlas)As of: Jul 6, 2026
- CAReport cited by Compute AtlasAs of: Jul 24, 2026
- CAData Center Dynamics (cited by Compute Atlas)As of: Aug 5, 2026
- SCServer Country project record (CC BY 4.0)As of: Sep 24, 2026 · Record: 0170
- KWKapwork Grow tracker record, merged from the sources listed here (free account)As of: Sep 23, 2026 · Record: 255429886652030
Limitations and interpretation
- This record is the Kapwork Grow tracker's merged view of a facility, from the tracker snapshot built 2026-09-23. Facts tagged KW are the tracker's resolved values; the per-source rows it was merged from are listed under Sources and on the tracker record.
- Sources on this record: Compute Atlas: Kubiak, E. (2026). Compute Atlas [Data set]. https://doi.org/10.5281/zenodo.22284476 (CC BY 4.0) · Server Country, https://servercountry.org/data/ (CC BY 4.0). Every source is licensed for commercial use with attribution.
- An announced or permitted build is not a contract, an open bid or a purchase order.
- Capacity figures are as reported by the cited sources and may describe planned rather than energised capacity.
Cite or correct this record
Kapwork Grow, “Meta Jeffersonville Data Center”, https://kapwork.com/grow/directory/datacenters/meta-jeffersonville-data-center-in-dc_e84fe7a8ae7e, materially updated Sep 24, 2026.
Report an error in this record and we will check it against the cited sources.
An announced or permitted build is not a contract, an open bid or a purchase order. Capacity and dates are as reported by the cited sources. “Not reported” means missing information, not zero. Completed and withdrawn records can remain available as historical records.